PRBD202513586
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed | 1/22/2026 (12:30 - 2:30) | 1/22/2026 (PM) | 01/22/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/22/2026
All framing approved
|
||||
| Above Ceiling Inspection | Passed w/ Conditions | 2/18/2026 (10:00 - 12:00) | 2/18/2026 (AM) | 02/18/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/18/2026
Above ceiling approved pending the correction listed in outstanding comments.
|
||||
|
Miscellaneous/Other
Outstanding
02/18/2026
The portion of wall above ceiling in corridor and extending into MDF room is not properly supported as per the requirements for deflection and post tension of this building.
2 options for correcting this…1) either remove the wall section completely, or 2) properly support this wall sect with kickers every 4 ft that attach to wall and anchored into concrete. Keep I mind this is post tension concrete above and fastener length and location may be an issue to not hit any cables running through the post tensioned concrete. The contractor can decide on which they would like to do to remedy this correction.
Will review this correction at next inspection.
|
||||
| Fire Inspection Final | Passed | 03/26/2026 | ||
| Building Final Inspection | Passed | 3/27/2026 (12:30 - 2:30) | 3/27/2026 (PM) | 03/27/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/27/2026
Final approved for this buildout.
|
||||