PRBD202514713
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed | 12/16/2025 (12:30 - 2:30) | 12/16/2025 (PM) | 12/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/16/2025
Framing approved
|
||||
| Above Ceiling Inspection | Passed | 12/22/2025 (8:00 - 10:00) | 12/22/2025 (AM) | 12/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/22/2025
Above ceiling... approved
|
||||
| Fire Inspection Final | Partial Pass | 2/2/2026 (10:00 - 12:00) | 2/2/2026 (AM) | 02/02/2026 |
| Phase 1 ok. | ||||
| Building Final Inspection | Partial Pass | 2/2/2026 (10:00 - 12:00) | 2/2/2026 (AM) | 02/02/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/02/2026
Phase one of this tenant remodel approved for use.
|
||||
| Framing Inspection | Passed | 2/11/2026 (12:30 - 2:30) | 2/11/2026 (PM) | 02/11/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/11/2026
All framing approved.
|
||||
| Fire Inspection Final | Partial Pass | 2/26/2026 (8:00 - 10:00) | 2/26/2026 (AM) | 02/26/2026 |
|
Corrections:
Miscellaneous/Other
Carried Forward
02/26/2026
Add 3 exit signs.
|
||||
| Building Final Inspection | Not Ready | 2/26/2026 (8:00 - 10:00) | 2/26/2026 (AM) | 02/26/2026 |
|
Corrections:
Miscellaneous/Other
Carried Forward
02/26/2026
Corrections...
1) install exit signs as noted on the reflective ceiling plan. (2 directional and 1 at the exit door)
Set up final inspection when completed.
|
||||
| Fire Inspection Final | Passed | 3/2/2026 (10:00 - 12:00) | 3/2/2026 (AM) | 03/02/2026 |
|
Corrections:
Miscellaneous/Other
Outstanding
02/26/2026
Add 3 exit signs.
|
||||
| Building Final Inspection | Passed | 3/2/2026 (10:00 - 12:00) | 3/2/2026 (AM) | 03/02/2026 |
|
Corrections:
Miscellaneous/Other
Resolved
03/02/2026
Corrections...
1) install exit signs as noted on the reflective ceiling plan. (2 directional and 1 at the exit door)
Set up final inspection when completed.
|
||||
|
Miscellaneous/Other
Comment Only
03/02/2026
Exit signs installed... final for this permit and scope of work approved
|
||||