PRBD202600625
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Progress Inspection | Passed | 5/1/2026 (8:00 - 10:00) | 5/1/2026 (AM) | 05/01/2026 |
| Questions regarding doors(security doors) | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
05/01/2026
Went over exiting and door hardware for exit doors. Exiting and hardware is approved.
|
||||
| Progress Inspection | Not Ready | 5/1/2026 (8:00 - 10:00) | 5/1/2026 (AM) | 05/07/2026 |
| Framing Inspection | Passed | 5/11/2026 (10:00 - 12:00) | 5/11/2026 (AM) | 05/11/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/11/2026
Wall framing and finish... approved
|
||||
| Fire Inspection Final | Not Ready | 5/29/2026 (12:30 - 2:30) | 5/29/2026 (PM) | 05/29/2026 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/29/2026
Seal any penetrations in wall above ceiling.
Close any open junction boxes.
Replace missing ceiling tiles.
Add sprinkler heads in hoods.
Replace any missing ceiling tiles.
Hang one fire extinguisher in manufacture area and one in front office.
Remove grill from inside.
Replace any missing outlet covers.
Secure sprinkler head bracket to grid.
|
||||
| Building Final Inspection | Not Ready | 5/29/2026 (12:30 - 2:30) | 5/29/2026 (PM) | 05/29/2026 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/29/2026
Corrections...
1) open wiring to be enclosed in a junction box.
2)Install any missing ceiling sections and tiles.
3) hang fire extinguishers in front office and manufacture area.
4) remove BBQ grill and fuel tank from building.
5) install coverplates to outlet where missing
6)Secure sprinkle head bracket to grid
7) seal around penetrations at block wall and large hole in block wall... per fire inspection
8) install sprinkler heads in hoods... per fire inspection
Set up reinspection for building and fire when these items are completed.
|
||||
| Fire Inspection Final | Passed | 6/5/2026 (12:30 - 2:30) | 6/5/2026 (PM) | 06/05/2026 |
|
Corrections:
Miscellaneous/Other
Outstanding
05/29/2026
Seal any penetrations in wall above ceiling.
Close any open junction boxes.
Replace missing ceiling tiles.
Add sprinkler heads in hoods.
Replace any missing ceiling tiles.
Hang one fire extinguisher in manufacture area and one in front office.
Remove grill from inside.
Replace any missing outlet covers.
Secure sprinkler head bracket to grid.
|
||||
| Building Final Inspection | Issue CO | 6/5/2026 (12:30 - 2:30) | 6/5/2026 (PM) | 06/05/2026 |
|
Corrections:
Miscellaneous/Other
Resolved
06/05/2026
Corrections...
1) open wiring to be enclosed in a junction box.
2)Install any missing ceiling sections and tiles.
3) hang fire extinguishers in front office and manufacture area.
4) remove BBQ grill and fuel tank from building.
5) install coverplates to outlet where missing
6)Secure sprinkle head bracket to grid
7) seal around penetrations at block wall and large hole in block wall... per fire inspection
8) install sprinkler heads in hoods... per fire inspection
Set up reinspection for building and fire when these items are completed.
|
||||
|
Miscellaneous/Other
Comment Only
06/05/2026
All corrections are completed, this space is approved for the Certificate of Occupancy.
|
||||