PRBD202601579
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Pending | |||
| Fire Inspection Final | Pending | 4/6/2026 (8:00 - 10:00) | 4/6/2026 (AM) | |
| Framing Inspection | Passed | 3/17/2026 (8:00 - 10:00) | 3/17/2026 (AM) | 03/17/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/17/2026
Framing approved for this corridor relocation.
|
||||
| Building Final Inspection | Partial Pass | 4/6/2026 (8:00 - 10:00) | 4/6/2026 (AM) | 04/06/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/06/2026
Final approved, pending firestop at cast piping by entrance location and inside door at stairwell. Also need to take the partially buried junction box of of wall and surface mount it. Will recheck at next mall visit.
|
||||