PRCRF201700397
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 4/27/2017 (8:00 - 10:00) | 4/27/2017 | 04/27/2017 |
Corrections:
Miscellaneous/Other
Comment Only
04/27/2017
Viewed work in process. 2/3 of roof has been removed and reinsulated and covered. The Cap sheet and some metal finish has yet to be installed. Remaining old roofing to be replaced is held up due to weather. Ok to proceed.
|
||||
Building Final Inspection | Passed | 6/22/2017 (12:30 - 2:30) | 6/22/2017 | 06/22/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/22/2017
Final approved
|
||||
Progress Inspection | VOID | 10/17/2017 |