Permit Application Status

PRCRF201701168


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCRF201701168
Roof, Commercial
Finaled
BETHANY FELLOWSHIP INC
Repair/Replace
Remove existing roof membrane and insulation. Install ISO insulation to R-30. Install 2 additional scuppers. Install a fully adhered .60 mil black EPDM roofing system.Install outside perimeter metal.
03/07/2017
03/09/2017
09/15/2017
05/26/2017

Locations

Permits

Permit Number: PRCRF201701168

Roofing
Finaled
03/09/2017
09/15/2017

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Passed 3/15/2017 (10:00 - 12:00) 3/15/2017 03/15/2017
Corrections:


Miscellaneous/Other
Comment Only
03/15/2017
Progress inspection approved.

Building Final Inspection Passed 5/26/2017 (10:00 - 12:00) 5/26/2017 05/26/2017