PRCRF201804391
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Pending | |||
Progress Inspection | Partial Pass | 6/14/2018 (8:00 - 10:00) | 6/14/2018 | 06/14/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/14/2018
Progress inspection of roof section at loading dock location. Tear off and membrane being done, insulation to be as per plan incorporating the drainage sloping. All work is as per plan design.
|
||||
Building Final Inspection | Passed | 9/27/2018 (10:00 - 12:00) | 9/27/2018 | 09/27/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/27/2018
Roofing final approved
|