PRCRF201901078
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Progress Inspection | Pending | |||
Progress Inspection | Partial Pass | 5/24/2019 (8:00 - 10:00) | 5/24/2019 (AM) | 05/24/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/24/2019
Progress inspection of roofing at what is called “The Bat Wing” located behind Sears... approved. Roof area is still ongoing and more sections are to be done and metal installed at roof edge.
|
||||
Progress Inspection | Partial Pass | 12/3/2019 (8:00 - 10:00) | 12/3/2019 (AM) | 12/03/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/03/2019
Viewed a progress of the high south roof, the installation is ongoing and per mfg requirements. Approved.
|