PRCRF201902535
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Passed | 4/4/2019 (10:00 - 12:00) | 4/4/2019 (AM) | 04/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/04/2019
Removal of gravel and down to cleaner base for installation of 1 1/2” closed cell foam with built up roofing applied over top. Approved installation.
|
||||
Building Final Inspection | Passed | 5/10/2019 (8:00 - 10:00) | 5/10/2019 (AM) | 05/10/2019 |
Roof final- visual inspection from roof. | ||||
Corrections:
Miscellaneous/Other
Comment Only
05/10/2019
Final: work completed, visual inspection from roof.
|