PRCRF202104005
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Pending | 4/12/2023 (2:30 - 3:30) | ||
Building Final Inspection | Passed | 4/12/2023 (12:30 - 2:30) | 4/12/2023 (PM) | 04/12/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/12/2023
Photos of progress work were available from contractor. Warranty inspection was also performed and approved.
Final inspection viewing of the finished roof meets mfg requirements and is approved.
|