PRCRF202105554
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Progress Inspection | Passed | 7/22/2021 (12:30 - 2:30) | 7/22/2021 (PM) | 07/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/22/2021
Materials on site match the scope of work with products being installed. Most of roof is already set in place, and is covered. Approved to continue and finish roof. Call for final when all is completed.
|