PRCRF202106872
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Passed | 7/22/2021 (12:30 - 2:30) | 7/22/2021 (PM) | 07/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/22/2021
Euro- slip sheet and Durolast cover membrane installed to existing roof. Existing roof is still in tact and in good condition.
Progress of installation… approved
|
||||
Building Final Inspection | Passed | 8/19/2021 (10:00 - 12:00) | 8/19/2021 (AM) | 08/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
08/19/2021
Roofing final approved
|