PRCRF202211930
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Passed | 5/12/2023 (10:00 - 12:00) | 5/12/2023 (AM) | 05/12/2023 |
Corrections:
Miscellaneous/Other
Comment Only
05/12/2023
Progress inspection was not called in. Contractor informed of what was done insulation was added to bring up R- value of roof, extensions were added to any through piping and top membrame applied as per mfg specs. Rock was installed as required.
|
||||
Building Final Inspection | Passed | 5/12/2023 (10:00 - 12:00) | 5/12/2023 (AM) | 05/12/2023 |
Corrections:
Miscellaneous/Other
Comment Only
05/12/2023
All work completed, final approved
|