PRDE201701814
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Passed | 4/19/2017 (12:30 - 2:30) | 4/19/2017 | 04/19/2017 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2017
Demo completed. Any items leftover that deal with firestops, fire proofing, and patching of rated wall will be assigned to the contractor that has the buildout. In this instance the contractor is the same for demo and buildout.
|