PRDR201908191
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Driveway Final Inspection Public | Passed | 8/23/2019 | 08/30/2019 | |
| Engineering did not receive notice for a form inspection-therefore no form inspection was done. | ||||
| Driveway Final Inspection Private | Passed | 8/23/2019 | 09/05/2019 | |
| Driveway Form Inspection | VOID | 5/1/2020 | 10/06/2020 | |
| New driveway 10/6/20: Project completed last year. Sean J met with contractor and school principal after curb had been poured without a form inspection. That curb was removed and replaced later that same summer and passed final inspection. Saw that Form Inspection Activity was still open on 10/6/20 so am now closing out activity. | ||||