PREHP201905711
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
EH Final Inspection | Passed | 8/20/2019 (10:00 - 12:00) | 8/20/2019 | 08/27/2019 |
Corrections:
Miscellaneous/Other
Outstanding
08/20/2019
1. Provide nsf listing on cabinet
2. Seal underside of countertops
3. Provide concrete curb on electrical line penetration
Call for final. Ok to open. Final in 7 days.
|
||||
EH Final Inspection | Passed | 8/20/2019 (12:30 - 2:30) | 8/20/2019 (PM) | 08/27/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
08/20/2019
1. Provide nsf listing on cabinet
2. Seal underside of countertops
3. Provide concrete curb on electrical line penetration
Call for final. Ok to open. Final in 7 days.
|
||||
EH Progress Inspection | Passed | 08/27/2019 |