Permit Application Status

PREL201700169


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL201700169
Electrical
Finaled
STATION LLC
Alteration/Remodel
Remodel work at existing building, including remodel of restrooms, new chiller/mechanical equipment, new 350kw generator, new 3000A unit substation and remodel lower level office area/loading dock.
02/01/2017
02/10/2017
07/04/2018
01/05/2018

Locations

Permits

Permit Number: PREL201700169

Electrical
Finaled
02/10/2017
07/04/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 3/3/2017 (8:00 - 10:00) 3/3/2017 03/03/2017
Corrections:


Miscellaneous/Other
Comment Only
03/03/2017
RI - 12th floor restrooms.

Electrical Rough-in Inspection Partial Pass 3/28/2017 (8:00 - 10:00) 3/28/2017 03/28/2017
RI - 11th floor restrooms
Corrections:


Miscellaneous/Other
Outstanding
03/28/2017
RI - 11th floor restrooms

Electrical Final Inspection Partial Pass 4/5/2017 (8:00 - 10:00) 4/5/2017 04/05/2017
Corrections:


Miscellaneous/Other
Carried Forward
04/05/2017
Final - 12th floor restrooms

Electrical Rough-in Inspection Partial Pass 4/18/2017 04/18/2017
UG installation of PVC conduits under existing loading dock area to new chiller and generator locations.
Electrical Final Inspection Partial Pass 4/21/2017 (8:00 - 10:00) 4/21/2017 04/21/2017
Corrections:


Miscellaneous/Other
Comment Only
04/21/2017
Final - 11th floor restrooms

Electrical Rough-in Inspection Partial Pass 5/1/2017 (2:30 - 3:30) 5/1/2017 05/01/2017
Corrections:


Outstanding
04/21/2017
Final - 11th floor restrooms.

Miscellaneous/Other
Comment Only
05/01/2017
10th floor bathrooms - RI -OK

Electrical Rough-in Inspection Partial Pass 5/9/2017 (12:30 - 2:30) 5/9/2017 05/09/2017
Corrections:


Miscellaneous/Other
Comment Only
05/09/2017
RI - 1st floor vestibule.

Electrical Rough-in Inspection Partial Pass 5/19/2017 (12:30 - 2:30) 5/19/2017 05/19/2017
Corrections:


Miscellaneous/Other
Comment Only
05/19/2017
RI - 9th floor restrooms.

Electrical Final Inspection Partial Pass 5/24/2017 (8:00 - 10:00) 5/24/2017 05/24/2017
Corrections:


Miscellaneous/Other
Carried Forward
05/24/2017
Final - 10th floor restrooms

Electrical Final Inspection Partial Pass 6/14/2017 (10:00 - 12:00) 6/14/2017 06/14/2017
Corrections:


Miscellaneous/Other
Comment Only
06/14/2017
Final - 9th floor restrooms.

Electrical Rough-in Inspection Partial Pass 6/20/2017 (12:30 - 2:30) 6/20/2017 06/20/2017
Corrections:


Miscellaneous/Other
Comment Only
06/20/2017
RI- 8th floor restrooms.

Electrical Rough-in Inspection Partial Pass 6/30/2017 (10:00 - 12:00) 6/30/2017 06/30/2017
Corrections:


Miscellaneous/Other
Comment Only
06/30/2017
RI - 13th floor restrooms. UG - chiller site.

Electrical Rough-in Inspection Partial Pass 7/11/2017 (10:00 - 12:00) 7/11/2017 07/11/2017
Corrections:


Miscellaneous/Other
Comment Only
07/11/2017
RI - 7th floor restrooms

Electrical Final Inspection Partial Pass 7/17/2017 (8:00 - 10:00) 7/17/2017 07/17/2017
Corrections:


Miscellaneous/Other
Comment Only
07/17/2017
Final - 8th floor restrooms

Electrical Final Inspection Partial Pass 7/25/2017 (8:00 - 10:00) 7/25/2017 07/25/2017
Corrections:


Miscellaneous/Other
Comment Only
07/25/2017
Final - 13th floor restrooms.

Electrical Rough-in Inspection Partial Pass 8/1/2017 (8:00 - 10:00) 8/1/2017 08/01/2017
Corrections:


Miscellaneous/Other
Comment Only
08/01/2017
RI - loading dock receiving room ceiling. Final - 7th floor restrooms.

Electrical Rough-in Inspection Partial Pass 8/11/2017 (10:00 - 12:00) 8/11/2017 08/11/2017
Corrections:


Miscellaneous/Other
Comment Only
08/11/2017
RI - 6th floor restrooms.

Electrical Rough-in Inspection Partial Pass 8/18/2017 (10:00 - 12:00) 8/18/2017 08/18/2017
Corrections:


Miscellaneous/Other
Comment Only
08/18/2017
New 13.8 feeder. RI - LL elevator lobby hard-lid ceilings.

Electrical Rough-in Inspection Partial Pass 8/21/2017 (10:00 - 12:00) 8/21/2017 08/21/2017
Corrections:


Miscellaneous/Other
Comment Only
08/21/2017
Lower level men's and women's bathroom RI OK. Including FA cable RI install.

Electrical Rough-in Inspection Partial Pass 9/1/2017 (10:00 - 12:00) 9/1/2017 09/01/2017
Corrections:


Miscellaneous/Other
Comment Only
09/01/2017
RI - 5th floor restrooms.

Electrical Rough-in Inspection Partial Pass 9/6/2017 (8:00 - 10:00) 9/6/2017 09/06/2017
Corrections:


Miscellaneous/Other
Comment Only
09/06/2017
Final - 6th floor restrooms.

Electrical Final Inspection VOID 8/2/2017 (8:00 - 10:00) 8/2/2017 09/06/2017
Electrical Final Inspection Partial Pass 9/14/2017 (8:00 - 10:00) 9/14/2017 09/14/2017
Corrections:


Miscellaneous/Other
Comment Only
09/14/2017
Final - lower level restrooms and elevator lobby.

Electrical Rough-in Inspection Partial Pass 9/28/2017 (12:30 - 2:30) 9/28/2017 09/29/2017
Corrections:


Miscellaneous/Other
Comment Only
09/28/2017
RI - 14th floor restrooms. Final - 5th floor restrooms.

Electrical Rough-in Inspection Partial Pass 10/6/2017 (10:00 - 12:00) 10/6/2017 10/09/2017
Corrections:


Miscellaneous/Other
Comment Only
10/09/2017
Final - 4th floor restrooms.

Electrical Final Inspection Partial Pass 10/13/2017 (8:00 - 10:00) 10/13/2017 10/13/2017
Move to Tim Miller's schedule, per Ric S.
Corrections:


Miscellaneous/Other
Comment Only
10/13/2017
14th floor bathrooms final OK

Electrical Rough-in Inspection Partial Pass 10/26/2017 (8:00 - 10:00) 10/26/2017 10/26/2017
Corrections:


Miscellaneous/Other
Comment Only
10/26/2017
RI - 3rd floor restrooms.

Electrical Final Inspection Partial Pass 10/26/2017 10/26/2017 10/26/2017
Corrections:


Miscellaneous/Other
Comment Only
10/26/2017
Final - 4th floor restrooms. RI - 3rd floor restrooms and FA.

Electrical Rough-in Inspection Partial Pass 11/6/2017 (7:00 - 8:00) 11/6/2017 11/06/2017
Corrections:


Miscellaneous/Other
Comment Only
11/06/2017
RI - 2nd floor restrooms.

Electrical Rough-in Inspection Partial Pass 11/21/2017 (12:30 - 2:30) 11/21/2017 11/21/2017
Corrections:


Miscellaneous/Other
Comment Only
11/21/2017
RI - 1st floor restrooms.

Electrical Final Inspection Partial Pass 11/21/2017 (12:30 - 2:30) 11/21/2017 11/21/2017
Corrections:


Miscellaneous/Other
Comment Only
11/21/2017
Final - 3rd floor restrooms

Electrical Final Inspection Partial Pass 12/5/2017 (8:00 - 10:00) 12/5/2017 12/05/2017
Corrections:


Miscellaneous/Other
Comment Only
12/05/2017
Final - 2nd floor restrooms

Electrical Final Inspection Partial Pass 12/13/2017 (8:00 - 10:00) 12/13/2017 12/13/2017
Corrections:


Miscellaneous/Other
Comment Only
12/13/2017
Final - 1st floor restrooms

Electrical Final Inspection Passed 12/15/2017 (8:00 - 10:00) 1/5/2018 01/05/2018
Passed per R.Soderstrom. Moe Amanda 01/05/2018 8:45 AM