PREL201706310
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 8/18/2017 (8:00 - 10:00) | 7/26/2017 | 07/26/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/26/2017
RI - walls: restrooms and 2 - offices.
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/18/2017 (12:30 - 2:30) | 8/18/2017 | 08/18/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/18/2017
Trench OK
|
||||
Miscellaneous/Other
Outstanding
08/18/2017
Verify and label available fault current at service
Provide documentation for fully or series rated system at panels- label accordingly.
|
||||
Miscellaneous/Other
Outstanding
08/18/2017
Provide protection of equipment at exterior of building- provide protection from physical damage.
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/24/2017 (12:30 - 2:30) | 8/24/2017 | 08/24/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/24/2017
Above ceiling OK - verbal continue to strap MC cable where needed.
Verbal to GC- remove abandoned limited energy cable. Plenum ceiling.
|
||||
Miscellaneous/Other
Outstanding
08/24/2017
Service in process of being installed.
Verify available fault current at service.
Verify series ratings of equipment.
Bond at CT cabinet and at main service.
Call for inspection when ready.
|
||||
Electrical Rough-in Inspection | Passed | 8/29/2017 (10:00 - 12:00) | 8/29/2017 | 08/29/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/29/2017
Service released to Xcel.
400 amp. 120/208 volt 3 phase.
|
||||
Electrical Final Inspection | Partial Pass | 10/5/2017 (8:00 - 10:00) | 10/5/2017 | 10/05/2017 |
Corrections:
Miscellaneous/Other
Outstanding
10/05/2017
Part pass-
Exit light at front entrance not functioning.
Complete protection of service conduit at rear exterior. Per GC - handrails to be installed yet, provide effective physical protection up to 18" in height- check when completed.
Call for final electrical inspection approvals when completed- within 15 working days.
|
||||
Electrical Final Inspection | Passed | 11/15/2017 (8:00 - 10:00) | 11/15/2017 | 11/15/2017 |