PREL201710520
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 12/11/2017 (10:00 - 12:00) | 12/11/2017 | 12/11/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/11/2017
Pool bonding (remodel to existing).
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/4/2018 (12:30 - 2:30) | 1/4/2018 | 01/04/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/04/2018
Atrium underground
Office wall RI
Lobby underground and wall RI
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/29/2018 (12:30 - 2:30) | 1/29/2018 | 01/29/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/29/2018
Trench and UG at atrium area OK
Bonding at fountains - visual OK - existing foundations- rebar bonding OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/7/2018 (8:00 - 10:00) | 2/7/2018 | 02/08/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/08/2018
Site meeting re: existing pool lighting and wet-niche light.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/15/2018 (8:00 - 10:00) | 2/15/2018 | 02/15/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/15/2018
RI - pool restrooms walls.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/26/2018 (2:30 - 3:30) | 2/26/2018 | 02/26/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/26/2018
Bonding of whirlpool.
|
||||
Electrical Rough-in Inspection | Failed | 3/12/2018 (12:30 - 2:30) | 3/12/2018 | 03/12/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
03/12/2018
Remove abandoned LV cables from restroom and lobby ceilings.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/14/2018 (2:30 - 3:30) | 3/14/2018 | 03/14/2018 |
Corrections:
Miscellaneous/Other
Outstanding
03/12/2018
Remove abandoned LV cables from restroom and lobby ceilings.
|
||||
Miscellaneous/Other
Comment Only
03/14/2018
RI - atrium center walls.
RI - atrium restroom ceilings and lobby cloud.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/20/2018 (12:30 - 2:30) | 3/20/2018 | 03/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/20/2018
RI - hot tub bonding. W beverage center. E fireplace wall.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/23/2018 (8:00 - 10:00) | 3/23/2018 | 03/23/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/23/2018
RI - atrium walls.
Partial final - 3 meeting rooms.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/28/2018 (8:00 - 10:00) | 3/28/2018 | 03/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/28/2018
RI - lobby reception desk walls.
Partial final - SW meeting rooms (2).
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/5/2018 (8:00 - 10:00) | 4/5/2018 | 04/05/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/05/2018
Pool wet-niche light.
Pool equipment bonding.
NE banquet room and pre-function ceilings.
|
||||
Electrical Final Inspection | Partial Pass | 4/10/2018 (2:30 - 3:30) | 4/10/2018 | 04/10/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/10/2018
RI - ceiling: NW banquet room.
|
||||
Electrical Final Inspection | Partial Pass | 4/19/2018 (10:00 - 12:00) | 4/19/2018 | 04/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2018
Final - reception desk, exercise room, SW meeting room.
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/24/2018 (8:00 - 3:30) | 4/24/2018 | 04/24/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/24/2018
Final - pool.
|
||||
Electrical Final Inspection | Partial Pass | 5/3/2018 (12:30 - 2:30) | 5/3/2018 | 05/03/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/03/2018
Final - public restrooms
|
||||
Electrical Rough-in Inspection | Partial Pass | 5/8/2018 (Afternoon) | 5/8/2018 | 05/08/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/08/2018
RI - CTO ceiling (partial); floor outlets: reception area.
|
||||
Electrical Final Inspection | Partial Pass | 5/16/2018 (12:30 - 2:30) | 5/16/2018 | 05/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/16/2018
Lower level of atrium OK to use.
|
||||
Electrical Rough-in Inspection | Partial Pass | 05/16/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/16/2018
RI of walls at cook to order area & "kitchen"
|
||||
Electrical Final Inspection | Partial Pass | 5/31/2018 (12:30 - 2:30) | 5/31/2018 | 05/31/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/31/2018
Final - Atrium. Ceiling: cook-to-order.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/20/2018 (8:00 - 10:00) | 6/20/2018 | 06/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/20/2018
Cook-to-order ceilings and outlets.
GFI-protect beer cooler outlet.
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/12/2018 (8:00 - 10:00) | 7/12/2018 | 07/12/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/12/2018
RI OK at serving area counters.
|
||||
Electrical Final Inspection | Partial Pass | 8/8/2018 (12:30 - 2:30) | 8/8/2018 | 08/08/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/08/2018
Partial final - OK to use the cook to,order area.
|
||||
Electrical Final Inspection | Partial Pass | 9/11/2018 (8:00 - 10:00) | 9/11/2018 | 09/12/2018 |
Corrections:
Miscellaneous/Other
Resolved
09/14/2018
Verify OCP at equipment in trash room.
|
||||
Electrical Final Inspection | Passed | 9/14/2018 (12:30 - 2:30) | 9/14/2018 | 09/14/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/14/2018
Final - complete.
|