Permit Application Status

PREL201710520


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL201710520
Electrical
Finaled
FELCOR/CSS HOLDINGS SPE
Alteration/Remodel
Remodel of main floor lobby and Atrium. Embassy Suites Hotel.
10/31/2017
11/01/2017
03/13/2019
09/14/2018

Locations

Permits

Permit Number: PREL201710520

Electrical
Finaled
11/01/2017
03/13/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 12/11/2017 (10:00 - 12:00) 12/11/2017 12/11/2017
Corrections:


Miscellaneous/Other
Comment Only
12/11/2017
Pool bonding (remodel to existing).

Electrical Rough-in Inspection Partial Pass 1/4/2018 (12:30 - 2:30) 1/4/2018 01/04/2018
Corrections:


Miscellaneous/Other
Comment Only
01/04/2018
Atrium underground Office wall RI Lobby underground and wall RI

Electrical Rough-in Inspection Partial Pass 1/29/2018 (12:30 - 2:30) 1/29/2018 01/29/2018
Corrections:


Miscellaneous/Other
Comment Only
01/29/2018
Trench and UG at atrium area OK Bonding at fountains - visual OK - existing foundations- rebar bonding OK

Electrical Rough-in Inspection Partial Pass 2/7/2018 (8:00 - 10:00) 2/7/2018 02/08/2018
Corrections:


Miscellaneous/Other
Comment Only
02/08/2018
Site meeting re: existing pool lighting and wet-niche light.

Electrical Rough-in Inspection Partial Pass 2/15/2018 (8:00 - 10:00) 2/15/2018 02/15/2018
Corrections:


Miscellaneous/Other
Comment Only
02/15/2018
RI - pool restrooms walls.

Electrical Rough-in Inspection Partial Pass 2/26/2018 (2:30 - 3:30) 2/26/2018 02/26/2018
Corrections:


Miscellaneous/Other
Comment Only
02/26/2018
Bonding of whirlpool.

Electrical Rough-in Inspection Failed 3/12/2018 (12:30 - 2:30) 3/12/2018 03/12/2018
Corrections:


Miscellaneous/Other
Carried Forward
03/12/2018
Remove abandoned LV cables from restroom and lobby ceilings.

Electrical Rough-in Inspection Partial Pass 3/14/2018 (2:30 - 3:30) 3/14/2018 03/14/2018
Corrections:


Miscellaneous/Other
Outstanding
03/12/2018
Remove abandoned LV cables from restroom and lobby ceilings.

Miscellaneous/Other
Comment Only
03/14/2018
RI - atrium center walls. RI - atrium restroom ceilings and lobby cloud.

Electrical Rough-in Inspection Partial Pass 3/20/2018 (12:30 - 2:30) 3/20/2018 03/20/2018
Corrections:


Miscellaneous/Other
Comment Only
03/20/2018
RI - hot tub bonding. W beverage center. E fireplace wall.

Electrical Rough-in Inspection Partial Pass 3/23/2018 (8:00 - 10:00) 3/23/2018 03/23/2018
Corrections:


Miscellaneous/Other
Comment Only
03/23/2018
RI - atrium walls. Partial final - 3 meeting rooms.

Electrical Rough-in Inspection Partial Pass 3/28/2018 (8:00 - 10:00) 3/28/2018 03/28/2018
Corrections:


Miscellaneous/Other
Comment Only
03/28/2018
RI - lobby reception desk walls. Partial final - SW meeting rooms (2).

Electrical Rough-in Inspection Partial Pass 4/5/2018 (8:00 - 10:00) 4/5/2018 04/05/2018
Corrections:


Miscellaneous/Other
Comment Only
04/05/2018
Pool wet-niche light. Pool equipment bonding. NE banquet room and pre-function ceilings.

Electrical Final Inspection Partial Pass 4/10/2018 (2:30 - 3:30) 4/10/2018 04/10/2018
Corrections:


Miscellaneous/Other
Comment Only
04/10/2018
RI - ceiling: NW banquet room.

Electrical Final Inspection Partial Pass 4/19/2018 (10:00 - 12:00) 4/19/2018 04/19/2018
Corrections:


Miscellaneous/Other
Comment Only
04/19/2018
Final - reception desk, exercise room, SW meeting room.

Electrical Rough-in Inspection Partial Pass 4/24/2018 (8:00 - 3:30) 4/24/2018 04/24/2018
Corrections:


Miscellaneous/Other
Comment Only
04/24/2018
Final - pool.

Electrical Final Inspection Partial Pass 5/3/2018 (12:30 - 2:30) 5/3/2018 05/03/2018
Corrections:


Miscellaneous/Other
Comment Only
05/03/2018
Final - public restrooms

Electrical Rough-in Inspection Partial Pass 5/8/2018 (Afternoon) 5/8/2018 05/08/2018
Corrections:


Miscellaneous/Other
Comment Only
05/08/2018
RI - CTO ceiling (partial); floor outlets: reception area.

Electrical Final Inspection Partial Pass 5/16/2018 (12:30 - 2:30) 5/16/2018 05/16/2018
Corrections:


Miscellaneous/Other
Comment Only
05/16/2018
Lower level of atrium OK to use.

Electrical Rough-in Inspection Partial Pass 05/16/2018
Corrections:


Miscellaneous/Other
Comment Only
05/16/2018
RI of walls at cook to order area & "kitchen"

Electrical Final Inspection Partial Pass 5/31/2018 (12:30 - 2:30) 5/31/2018 05/31/2018
Corrections:


Miscellaneous/Other
Comment Only
05/31/2018
Final - Atrium. Ceiling: cook-to-order.

Electrical Rough-in Inspection Partial Pass 6/20/2018 (8:00 - 10:00) 6/20/2018 06/20/2018
Corrections:


Miscellaneous/Other
Comment Only
06/20/2018
Cook-to-order ceilings and outlets. GFI-protect beer cooler outlet.

Electrical Rough-in Inspection Partial Pass 7/12/2018 (8:00 - 10:00) 7/12/2018 07/12/2018
Corrections:


Miscellaneous/Other
Comment Only
07/12/2018
RI OK at serving area counters.

Electrical Final Inspection Partial Pass 8/8/2018 (12:30 - 2:30) 8/8/2018 08/08/2018
Corrections:


Miscellaneous/Other
Comment Only
08/08/2018
Partial final - OK to use the cook to,order area.

Electrical Final Inspection Partial Pass 9/11/2018 (8:00 - 10:00) 9/11/2018 09/12/2018
Corrections:


Miscellaneous/Other
Resolved
09/14/2018
Verify OCP at equipment in trash room.

Electrical Final Inspection Passed 9/14/2018 (12:30 - 2:30) 9/14/2018 09/14/2018
Corrections:


Miscellaneous/Other
Comment Only
09/14/2018
Final - complete.