PREL201711210
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 11/29/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/29/2017
Partial pass- wall RI - see orange card for areas
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/1/2017 (8:00 - 10:00) | 12/1/2017 | 12/01/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/01/2017
RI - walls (phase 1).
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/11/2017 (10:00 - 12:00) | 12/11/2017 | 12/11/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/11/2017
Phase 2 ceiling OK for power and lighting.
|
||||
Electrical Rough-in Inspection | Passed | 1/4/2018 (10:00 - 12:00) | 1/4/2018 | 01/04/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/04/2018
Ceiling RI three rooms
|
||||
Electrical Final Inspection | Partial Pass | 1/10/2018 (8:00 - 10:00) | 1/10/2018 | 01/10/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/10/2018
Part pass- verify exit and EM lighting at final
|
||||
Electrical Rough-in Inspection | Passed | 1/17/2018 (10:00 - 12:00) | 1/17/2018 | 01/17/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2018
West wall RI- OK
Completion to be on the ongoing project and 1st quarter maintenance permit.
|
||||
Electrical Final Inspection | Passed | 2/14/2018 (8:00 - 10:00) | 01/17/2018 | |
Electrical Final Inspection | Passed | 2/14/2018 (8:00 - 10:00) | 2/14/2018 | 02/14/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/14/2018
Warehouse office- final OK
Limited view and access above ceiling.
|