Summary

PREL201801292
Electrical
Finaled
PARTNERS LLC
Alteration/Remodel
(6) lights, (7) switches, (28) receptacles, & (12) 20a circuits.
02/14/2018
02/16/2018
11/07/2018
05/11/2018

Locations

Permits

Permit Number: PREL201801292

Electrical
Finaled
02/16/2018
11/07/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 2/21/2018 (8:00 - 10:00) 2/21/2018 02/21/2018
Corrections:


Miscellaneous/Other
Comment Only
02/21/2018
RI - walls.

Electrical Rough-in Inspection Passed 3/7/2018 (2:30 - 3:30) 3/7/2018 03/07/2018
Corrections:


Miscellaneous/Other
Comment Only
03/07/2018
RI - ceilings

Electrical Final Inspection Partial Pass 3/28/2018 (10:00 - 12:00) 3/28/2018 03/28/2018
Corrections:


Miscellaneous/Other
Comment Only
03/28/2018
Partial final - linear lighting to install.