PREL201801292
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 2/21/2018 (8:00 - 10:00) | 2/21/2018 | 02/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/21/2018
RI - walls.
|
||||
Electrical Rough-in Inspection | Passed | 3/7/2018 (2:30 - 3:30) | 3/7/2018 | 03/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/07/2018
RI - ceilings
|
||||
Electrical Final Inspection | Partial Pass | 3/28/2018 (10:00 - 12:00) | 3/28/2018 | 03/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/28/2018
Partial final - linear lighting to install.
|
||||
Electrical Final Inspection | Passed | 5/11/2018 | 05/11/2018 |