Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 3/28/2018 (10:00 - 12:00) | 3/28/2018 | 03/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/28/2018
RI - walls.
Provide access to existing j-box above new hard-lid.
|
||||
Electrical Rough-in Inspection | Passed | 5/11/2018 (12:30 - 2:30) | 5/11/2018 | 05/11/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/11/2018
RI OK At hard lid ceiling.
|
||||
Electrical Final Inspection | Passed | 5/18/2018 (8:00 - 10:00) | 5/18/2018 | 05/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/18/2018
Final OK
Install breaker lock on at EM circuit.
|