PREL201802438
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Underground Electrical Inspection | Partial Pass | 4/18/2018 (8:00 - 10:00) | 4/18/2018 | 04/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/18/2018
UG - partial feeders to mechanical and pool equipment rooms.
|
||||
Underground Electrical Inspection | Partial Pass | 5/7/2018 (2:30 - 3:30) | 5/7/2018 | 05/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/07/2018
UG - service
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/4/2018 (12:30 - 2:30) | 9/4/2018 | 09/04/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/04/2018
Bonding at conductive pool shell, step, hand rail cup and wet niche Qty. 2 - all OK.
Install #8 insulated copper bonding jumper in nonmetallic raceway to wet niche luminaries.
Install approved potting compound.
Note - termination must comply with 680.24 for junction box or enclosure.
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/28/2018 (8:00 - 10:00) | 9/28/2018 | 09/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2018
Discussion of working clearance at main service.
One entrance to workspace allowed where double the required clearance is provided.
|
||||
Miscellaneous/Other
Comment Only
09/28/2018
5th floor corridor for lighting and homeruns. RI OK
|
||||
Underground Electrical Inspection | Partial Pass | 10/16/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/16/2018
Site inspection at south parking lot
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/16/2018 (8:00 - 10:00) | 10/16/2018 | 10/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/16/2018
5th and 4th floor corridors RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/19/2018 (8:00 - 10:00) | 10/19/2018 | 10/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/19/2018
Units -RI OK @ 5th floor from elevator lobby east.
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/29/2018 (8:00 - 10:00) | 10/29/2018 (AM) | 10/29/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/29/2018
RI - 5th floor units west of elevators OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/1/2018 (10:00 - 12:00) | 11/1/2018 (AM) | 11/01/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/01/2018
2nd floor corridor RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/15/2018 (10:00 - 12:00) | 11/15/2018 (AM) | 11/15/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/15/2018
4th floor units and corridor RI OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/19/2018 (12:30 - 2:30) | 11/19/2018 (PM) | 11/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/19/2018
RI 3rd floor units east to elevator lobby OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/21/2018 (10:00 - 12:00) | 11/21/2018 (AM) | 11/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
11/21/2018
RI Units and corridor for 3rd floor OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/6/2018 (10:00 - 12:00) | 12/6/2018 (AM) | 12/06/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/06/2018
2nd floor corridor and units west to east except for last 5 units on east side not complete- RI OK except as noted. Contractor will call for additional inspection.
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/12/2018 (8:00 - 10:00) | 12/12/2018 (AM) | 12/12/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/12/2018
2nd floor units RI OK- complete.
PBX room - RI OK.
Stairwells RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/13/2018 (12:30 - 2:30) | 12/13/2018 (PM) | 12/13/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/13/2018
5th floor soffits at units OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/19/2018 (12:30 - 2:30) | 12/19/2018 (PM) | 12/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/19/2018
Pool deck bonding OK. Bonding of cups OK.
Bonding tail for ADA lift OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/4/2019 (12:30 - 2:30) | 1/4/2019 (PM) | 01/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
01/04/2019
RI OK- 1st floor units.
Sprinkler riser room RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/7/2019 (8:00 - 10:00) | 1/7/2019 (AM) | 01/07/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/27/2018
4th floor soffits except for south bathrooms where there are shaft walls.
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/14/2019 (10:00 - 12:00) | 1/14/2019 (AM) | 01/14/2019 |
Corrections:
Miscellaneous/Other
Comment Only
01/14/2019
Walls OK, at first floor common areas.
|
||||
Electrical Rough-in Inspection | Partial Pass | 1/17/2019 (10:00 - 12:00) | 1/17/2019 (AM) | 01/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2019
3rd floor soffits @units OK except at shaft walls.
|
||||
Electrical Rough-in Inspection | Partial Pass | 01/25/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
01/25/2019
Remainder of drop ceilings/ soffits at units on 5th floor. RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/8/2019 (12:30 - 2:30) | 2/8/2019 (PM) | 02/08/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/08/2019
RI OK at 4th and 5th floor corridor hard lid ceilings.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/20/2019 (8:00 - 10:00) | 2/20/2019 (AM) | 02/20/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/20/2019
RI at hard lid ceilings- 4 and 5th remaining soffits and ceiling OK.
3rd floor corridor hard lid and unit hard lid ceilings at units OK.
2nd floor unit hard lids OK.
|
||||
Electrical Rough-in Inspection | Failed | 02/20/2019 | ||
Corrections:
Miscellaneous/Other
Carried Forward
02/20/2019
Luminaries that were spot checked- no NRTL listing or certification label.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/28/2019 (10:00 - 12:00) | 2/28/2019 (AM) | 02/28/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/28/2019
Spoke to site superintendent for the GC in regards to unlisted luminaries.
|
||||
Miscellaneous/Other
Comment Only
02/28/2019
Approved 2nd floor corridor hard, misc hard lids on 3rd, 4th, and 5th floor east.
Hard lid 4th floor corridor at outside elevator lobby.
3rd floor south remaining hard lid at corridor.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/6/2019 (12:30 - 2:30) | 3/6/2019 (PM) | 03/06/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
03/06/2019
Luminaries that were spot checked- no NRTL listing or certification label.
|
||||
Miscellaneous/Other
Comment Only
03/06/2019
RI OK at hard lids at 1st floor units- south
|
||||
Miscellaneous/Other
Comment Only
03/06/2019
Service pre-inspection OK. 4000 A UG COMMERCIAL- 120/208 3phase.
Verify and post available fault current at service.
Verify and label at all series rated panels.
Bond at CT cabinet- verbal- provide photos.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/13/2019 (8:00 - 10:00) | 3/13/2019 (AM) | 03/13/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
03/13/2019
Luminaries that were spot checked- no NRTL listing or certification label.
|
||||
Miscellaneous/Other
Comment Only
03/13/2019
5th floor drop ceiling RI OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/26/2019 (10:00 - 12:00) | 3/26/2019 (AM) | 03/26/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
03/27/2019
Luminaries that were spot checked- no NRTL listing or certification label.
|
||||
Miscellaneous/Other
Comment Only
03/26/2019
03/26/2019. 3rd and 4th floor corridor drop ceilings RI OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/27/2019 (10:00 - 12:00) | 3/27/2019 (AM) | 03/27/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/27/2019
Partial pass of hard lid around pool.
Verbal bond to code - and call for reinspection.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/28/2019 (10:00 - 12:00) | 3/28/2019 (AM) | 03/28/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
03/28/2019
Luminaries that were spot checked- no NRTL listing or certification label.
|
||||
Miscellaneous/Other
Comment Only
03/28/2019
Bonding above pool area in ceiling- OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/1/2019 (10:00 - 12:00) | 4/1/2019 (AM) | 04/01/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
04/01/2019
Luminaries that were spot checked- no NRTL listing or certification label.
|
||||
Miscellaneous/Other
Comment Only
04/01/2019
RI OK at hard lid 1st floor corridor near units at south
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/9/2019 (8:00 - 10:00) | 4/9/2019 (AM) | 04/09/2019 |
Corrections:
Miscellaneous/Other
Resolved
04/09/2019
Luminaries that were spot checked- no NRTL listing or certification label.
|
||||
Miscellaneous/Other
Comment Only
04/09/2019
2nd floor corridor ceilings OK. Lobby area above hard lid OK. Electrical room ceiling OK.
Kitchen pantry above ceiling OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 05/06/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/06/2019
5th floor units on south wing - plug check OK
|
||||
Miscellaneous/Other
Comment Only
05/07/2019
5th floor units on south wing - plug check OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 5/16/2019 (8:00 - 10:00) | 5/16/2019 (AM) | 05/16/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/16/2019
Entry canopy - ceiling RI OK. First level above drop ceilings in common areas RI OK.
3rd floor south/west units plug check OK.
5th, 4th, and 3rd SW units all plug checked-OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 05/23/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/23/2019
3rd floor units- plug checks OK
|
||||
Miscellaneous/Other
Carried Forward
05/23/2019
Inspector needs to verify/ view listing marks at wall sconces and mirror lights.
|
||||
Electrical Rough-in Inspection | Failed | 05/24/2019 | ||
Corrections:
Miscellaneous/Other
Carried Forward
05/28/2019
Inspector needs to verify/ view listing marks at wall sconces and mirror lights.
|
||||
Miscellaneous/Other
Carried Forward
05/28/2019
Based on site visit on 05/24/2019
It appears that mirror luminaries are not listed.
Inspector referral to MN DLI website for equipment approval- and possible independent third party evaluation.
|
||||
Electrical Rough-in Inspection | Partial Pass | 05/28/2019 | ||
Corrections:
Miscellaneous/Other
Carried Forward
05/28/2019
Inspector needs to verify/ view listing marks at wall sconces and mirror lights.
|
||||
Miscellaneous/Other
Carried Forward
05/28/2019
Based on site visit on 05/24/2019
It appears that mirror luminaries are not listed.
Inspector referral to MN DLI website for equipment approval- and possible independent third party evaluation.
|
||||
Miscellaneous/Other
Comment Only
05/28/2019
Plug checks at 2nd floor units -south OK
|
||||
Underground Electrical Inspection | Passed | 06/06/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/06/2019
Trench and UG inspections where made as available and needed
|
||||
Electrical Rough-in Inspection | Partial Pass | 06/06/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/06/2019
RI Inspection essentially complete. Leaving open until only performing final inspection.
|
||||
Miscellaneous/Other
Comment Only
06/06/2019
2nd floor units plug checks OK
|
||||
Electrical Final Inspection | Partial Pass | 6/18/2019 (8:00 - 10:00) | 6/18/2019 (AM) | 06/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/18/2019
Inspector needs to verify/ view listing marks at wall sconces and mirror lights.
|
||||
Miscellaneous/Other
Carried Forward
06/19/2019
Based on site visit on 05/24/2019
It appears that mirror luminaries are not listed.
Inspector referral to MN DLI website for equipment approval- and possible independent third party evaluation.
|
||||
Miscellaneous/Other
Comment Only
06/18/2019
Progress inspection-'part pass... roof top installations OK.
|
||||
Miscellaneous/Other
Carried Forward
06/19/2019
Verify SCCR ratings at transfer switch equipment- see nameplate- specific type circuit breaker note for various ratings.
|
||||
Electrical Final Inspection | Partial Pass | 6/21/2019 (8:00 - 10:00) | 6/21/2019 (AM) | 06/21/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2019
Based on site visit on 05/24/2019
It appears that mirror luminaries are not listed.
Inspector referral to MN DLI website for equipment approval- and possible independent third party evaluation.
|
||||
Miscellaneous/Other
Carried Forward
07/02/2019
Verify SCCR ratings at transfer switch equipment- see nameplate- specific type circuit breaker note for various ratings.
|
||||
Miscellaneous/Other
Comment Only
06/21/2019
Progress inspection-partial final
Corridors at 2-5th floor OK, guest laundry OK
Hotel laundry OK. Elevator lobby 2-5th OK
|
||||
Electrical Rough-in Inspection | Passed | 07/01/2019 | ||
Electrical Final Inspection | Partial Pass | 07/02/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/02/2019
Partial final- all units have been plug checked.
|
||||
Electrical Final Inspection | Partial Pass | 7/11/2019 (8:00 - 10:00) | 7/11/2019 (AM) | 07/11/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
07/11/2019
Verify SCCR ratings at transfer switch equipment- see nameplate- specific type circuit breaker note for various ratings.
|
||||
Miscellaneous/Other
Comment Only
07/11/2019
Generator test OK
|
||||
Miscellaneous/Other
Comment Only
07/11/2019
Kitchen and eating areas OK
|
||||
Miscellaneous/Other
Carried Forward
07/11/2019
"Enter" sign at South entrance lacks required listing label, nameplate and disconnect means.
|
||||
Miscellaneous/Other
Carried Forward
07/11/2019
Pool equipment panel requires insulated copper equipment grounding conductor.
|
||||
Lighting Inspection | Passed | 08/07/2019 | ||
Holiday Inn Express Hotel 6/4/19 - Not lit | ||||
Electrical Final Inspection | Passed | 8/7/2019 (2:30 - 3:30) | 8/7/2019 (PM) | 08/07/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/07/2019
Verify SCCR ratings at transfer switch equipment- see nameplate- specific type circuit breaker note for various ratings.
|
||||
Miscellaneous/Other
Comment Only
08/07/2019
"Enter" sign at South entrance lacks required listing label, nameplate and disconnect means.
|
||||
Miscellaneous/Other
Comment Only
08/07/2019
Pool equipment panel requires insulated copper equipment grounding conductor.
|