Permit Application Status

PREL201803166


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL201803166
Electrical
Finaled
MINNESOTA CENTER JV LLC
Repair/Replace
Office build out of 4th,5th and 6th floor.
04/12/2018
04/13/2018
01/15/2019
07/19/2018

Locations

Permits

Permit Number: PREL201803166

Electrical
Finaled
04/13/2018
01/15/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 4/19/2018 (12:30 - 2:30) 4/19/2018 04/19/2018
Corrections:


Miscellaneous/Other
Comment Only
04/19/2018
5th floor wall ri

Electrical Rough-in Inspection Partial Pass 4/26/2018 (12:30 - 2:30) 4/26/2018 04/26/2018
Corrections:


Miscellaneous/Other
Comment Only
04/26/2018
4th floor wall ri

Electrical Rough-in Inspection Partial Pass 5/18/2018 (12:30 - 2:30) 5/18/2018 05/18/2018
Corrections:


Miscellaneous/Other
Comment Only
05/18/2018
6th floor wall RI complete.

Electrical Rough-in Inspection Partial Pass 6/8/2018 (12:30 - 2:30) 6/8/2018 06/08/2018
Corrections:


Miscellaneous/Other
Comment Only
06/08/2018
5th floor ceiling ri

Electrical Rough-in Inspection Partial Pass 6/13/2018 (12:30 - 2:30) 6/13/2018 06/13/2018
Corrections:


Miscellaneous/Other
Comment Only
06/13/2018
4th floor ceiling ri

Electrical Rough-in Inspection Partial Pass 6/20/2018 (12:30 - 2:30) 6/20/2018 06/20/2018
Corrections:


Miscellaneous/Other
Comment Only
06/20/2018
6th floor ceiling RI

Electrical Rough-in Inspection Partial Pass 6/21/2018 (12:30 - 2:30) 6/21/2018 06/21/2018
Corrections:


Miscellaneous/Other
Comment Only
06/21/2018
5th floor partial final

Electrical Final Inspection Partial Pass 6/26/2018 (12:30 - 2:30) 6/26/2018 06/26/2018
Corrections:


Miscellaneous/Other
Comment Only
06/26/2018
Partial final 4th and 5 th floor

Electrical Final Inspection Partial Pass 6/28/2018 (10:00 - 12:00) 6/28/2018 06/28/2018
Corrections:


Miscellaneous/Other
Outstanding
06/28/2018
6th floor not ready for final

Electrical Final Inspection Passed 7/19/2018 (2:30 - 3:30) 7/19/2018 07/19/2018