PREL201803166
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 4/19/2018 (12:30 - 2:30) | 4/19/2018 | 04/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2018
5th floor wall ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/26/2018 (12:30 - 2:30) | 4/26/2018 | 04/26/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/26/2018
4th floor wall ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 5/18/2018 (12:30 - 2:30) | 5/18/2018 | 05/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/18/2018
6th floor wall RI complete.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/8/2018 (12:30 - 2:30) | 6/8/2018 | 06/08/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/08/2018
5th floor ceiling ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/13/2018 (12:30 - 2:30) | 6/13/2018 | 06/13/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/13/2018
4th floor ceiling ri
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/20/2018 (12:30 - 2:30) | 6/20/2018 | 06/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/20/2018
6th floor ceiling RI
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/21/2018 (12:30 - 2:30) | 6/21/2018 | 06/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2018
5th floor partial final
|
||||
Electrical Final Inspection | Partial Pass | 6/26/2018 (12:30 - 2:30) | 6/26/2018 | 06/26/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/26/2018
Partial final 4th and 5 th floor
|
||||
Electrical Final Inspection | Partial Pass | 6/28/2018 (10:00 - 12:00) | 6/28/2018 | 06/28/2018 |
Corrections:
Miscellaneous/Other
Outstanding
06/28/2018
6th floor not ready for final
|
||||
Electrical Final Inspection | Passed | 7/19/2018 (2:30 - 3:30) | 7/19/2018 | 07/19/2018 |