PREL201804265
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Passed w/ Conditions | 5/22/2018 (10:00 - 12:00) | 5/22/2018 | 05/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/22/2018
NO RI - contractor called for final only
|
||||
Electrical Final Inspection | Not Ready | 5/29/2018 | 05/29/2018 | |
set time 10 meet contractor on site | ||||
Corrections:
Miscellaneous/Other
Comment Only
05/29/2018
Re-schedule for 05/30/2018
|
||||
Electrical Final Inspection | VOID | 05/29/2018 | ||
Electrical Final Inspection | Passed | 5/30/2018 (10:00 - 12:00) | 5/30/2018 | 05/30/2018 |
Corrections:
Miscellaneous/Other
Comment Only
05/22/2018
Limited view and access- no RI inspection called for.
Visual only- visual OK
|
||||
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified
Resolved
05/30/2018
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified.
Verify listing of equipment.
|