PREL201805664
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 7/3/2018 (2:30 - 3:30) | 7/3/2018 | 07/03/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/03/2018
Progress inspection- 1st floor men's bathroom near elevators- wall RI OK. Phased project -additional RI inspections pending.
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/17/2018 (10:00 - 12:00) | 7/17/2018 | 07/17/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/17/2018
Above ceiling RI OK at hard lid ceiling at 1st floor men's bathroom.
|
||||
Electrical Rough-in Inspection | Passed | 8/30/2018 (10:00 - 12:00) | 8/30/2018 | 08/30/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/30/2018
Wall RI OK at women's restroom-1st floor
OK to close up hard lid ceiling.
Check above ceiling at next inspection.
|
||||
Electrical Final Inspection | Passed | 9/14/2018 (10:00 - 12:00) | 9/14/2018 | 09/14/2018 |