Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Passed | 12/3/2018 (12:30 - 2:30) | 12/3/2018 (PM) | 12/03/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/03/2018
Walk through with contractor-east side.
|
||||
Electrical Final Inspection | Partial Pass | 12/4/2018 (12:30 - 2:30) | 12/4/2018 (PM) | 12/04/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/04/2018
Progress inspection- walk through with contractor.
|
||||
Electrical Final Inspection | Passed | 12/07/2018 |