PREL201806824
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 7/26/2018 (8:00 - 10:00) | 7/26/2018 | 07/26/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/26/2018
RI of theatre walls and ceiling only - OK
Separate permit to be pulled for FA and temp controls. GC made aware.
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/2/2018 (10:00 - 12:00) | 8/2/2018 | 08/02/2018 |
7/24/2018 inspection was canceled per Rick. ajacobson 07/31/2018 9:19 AM | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/02/2018
Wall RI
Show window receptacles needed
|
||||
Electrical Rough-in Inspection | Passed | 8/8/2018 (8:00 - 10:00) | 8/8/2018 | 08/08/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/08/2018
RI OK @ hard lid ceilings.
|
||||
Electrical Rough-in Inspection | Passed | 9/7/2018 (8:00 - 10:00) | 9/7/2018 | 09/07/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/07/2018
RI OK at raised floor in equipment room area.
|
||||
Miscellaneous/Other
Comment Only
09/07/2018
RI above drop ceiling OK- verbal to tie off independent support wires
|
||||
Electrical Final Inspection | Failed | 09/28/2018 | ||
Corrections:
Miscellaneous/Other
Carried Forward
09/28/2018
Site visit only.
Non plenum limited energy cables installed by tenant- remove all non rated cable.
All electrical installation is required to be performed by a State of Minnesota licensed contractor.
Call for new rough in inspection of this scope of work- this was given to the general contractor as a verbal order.
|
||||
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified
Carried Forward
09/28/2018
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified.
Independent third party evaluation is permitted for unlisted installations and equipment.
|
||||
Electrical Final Inspection | Partial Pass | 10/29/2018 (8:00 - 10:00) | 10/29/2018 (AM) | 10/29/2018 |
Corrections:
Miscellaneous/Other
Resolved
10/29/2018
Site visit only.
Non plenum limited energy cables installed by tenant- remove all non rated cable.
All electrical installation is required to be performed by a State of Minnesota licensed contractor.
Call for new rough in inspection of this scope of work- this was given to the general contractor as a verbal order.
|
||||
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified
Comment Only
10/29/2018
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified.
Independent third party evaluation is permitted for unlisted installations and equipment.
|
||||
Miscellaneous/Other
Carried Forward
10/29/2018
Electrical installation OK.
Need copy of independent third party evaluation for review. OK to stock or train.
|
||||
Electrical Final Inspection | Passed | 10/31/2018 | ||
Corrections:
Miscellaneous/Other
Resolved
10/31/2018
Electrical installation OK.
Need copy of independent third party evaluation for review. OK to stock or train.
|
||||
Miscellaneous/Other
Comment Only
10/31/2018
Independent third party evaluation received.
Final OK.
|