PREL201807509
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Failed | 8/6/2018 (8:00 - 10:00) | 8/6/2018 | 08/06/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
08/06/2018
Left voicemail message for contact- phone immediately went to message.
1st floor bathrooms- no access to women's- in use. Men's at 1st level- floor tile work in progress and no ladder on site.
Unable to verify other locations.
Schedule reinspection with additional information and access to areas.
|
||||
Electrical Rough-in Inspection | Passed | 8/22/2018 (10:00 - 12:00) | 8/22/2018 | 08/22/2018 |
Corrections:
Miscellaneous/Other
Resolved
08/22/2018
Left voicemail message for contact- phone immediately went to message.
1st floor bathrooms- no access to women's- in use. Men's at 1st level- floor tile work in progress and no ladder on site.
Unable to verify other locations.
Schedule reinspection with additional information and access to areas.
|
||||
Miscellaneous/Other
Comment Only
08/22/2018
RI and partial final OK
3rd floor at fitting rooms final OK.
Need to complete work at 1st floor restroom.
|
||||
Electrical Final Inspection | Partial Pass | 8/6/2018 (8:00 - 10:00) | 8/6/2018 | 08/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/22/2018
Partial pass OK- women's bathroom on 1st floor to complete. All else OK.
|
||||
Electrical Final Inspection | Passed | 12/17/2018 |