PREL201807610
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 8/9/2018 (12:30 - 2:30) | 8/9/2018 | 08/09/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/09/2018
RI OK @ underfloor/ walls and hard lid ceiling at ramped areas.
|
||||
Electrical Rough-in Inspection | Not Ready | 09/10/2018 | ||
Corrections:
Miscellaneous/Other
Carried Forward
09/10/2018
Site visit only. Verify NRTL certification of all electrical equipment and materials.
|
||||
Electrical Rough-in Inspection | Failed | 09/12/2018 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/12/2018
Site visit only. Verify NRTL certification of all electrical equipment and materials.
|
||||
Miscellaneous/Other
Comment Only
09/12/2018
Site visit only. Met with electrical contractor, general contractor, tenant and independent professional engineer to identify unlisted equipment, and wiring methods/materials.
|
||||
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified
Carried Forward
09/12/2018
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified- or independent third party evaluation by PE
|
||||
Electrical Rough-in Inspection | Passed | 9/20/2018 (10:00 - 12:00) | 9/20/2018 | 09/20/2018 |
Corrections:
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified
Comment Only
09/20/2018
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified- or independent third party evaluation by PE
|
||||
Electrical Final Inspection | Passed w/ Conditions | 9/26/2018 (8:00 - 10:00) | 9/26/2018 | 09/26/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/26/2018
Independent third party evaluation received - final contingent on acceptance.
|