Permit Application Status

PREL201808805


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL201808805
Electrical
Finaled
101 AMERICAN BLVD W LLC
New
Electrical for new storage facility.
08/07/2018
08/27/2018
02/23/2019
12/12/2019

Locations

Permits

Permit Number: PREL201808805

Electrical
Finaled
08/27/2018
02/23/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 3/13/2019 (8:00 - 10:00) 3/13/2019 (AM) 03/13/2019
Corrections:


Miscellaneous/Other
Comment Only
03/13/2019
Underground RI Talked about UHFER grounding

Electrical Rough-in Inspection Partial Pass 6/3/2019 (12:30 - 2:30) 6/3/2019 (PM) 06/03/2019
Corrections:


Miscellaneous/Other
Comment Only
06/03/2019
UG for gates- ok

Electrical Rough-in Inspection Partial Pass 6/4/2019 (10:00 - 12:00) 6/4/2019 (AM) 06/04/2019
Corrections:


Miscellaneous/Other
Comment Only
06/04/2019
Service UG- ok

Electrical Rough-in Inspection Partial Pass 6/17/2019 (8:00 - 10:00) 6/17/2019 (AM) 06/17/2019
Corrections:


Miscellaneous/Other
Comment Only
06/17/2019
Service- ok. Xcel contacted for connection. Need final connections to bond water. Did not see card to sign.

Miscellaneous/Other
Comment Only
06/17/2019
Lobby area wall RI - ok

Electrical Rough-in Inspection Partial Pass 6/24/2019 (8:00 - 3:30) 6/24/2019 (AM) 06/24/2019
Corrections:


Miscellaneous/Other
Comment Only
06/24/2019
Partial UG- photos ok of trench at parking lot for pole lights

Electrical Rough-in Inspection Partial Pass 8/7/2019 (8:00 - 10:00) 8/7/2019 (AM) 08/07/2019
Corrections:


Miscellaneous/Other
Comment Only
08/07/2019
Onsite meet for exits - ok

Electrical Rough-in Inspection Partial Pass 10/16/2019 (12:30 - 2:30) 10/16/2019 (PM) 10/16/2019
Canceled inspection, will reschedule in the future.NelsonThorpe Sarah 10/11/2019 1:27 PM
Corrections:


Miscellaneous/Other
Comment Only
10/16/2019
Em lighting all 3 floors-ok Walk through- ok RTU's - ok

Miscellaneous/Other
Carried Forward
10/16/2019
Signs, gates, and exterior lights.

Electrical Rough-in Inspection Partial Pass 11/4/2019 (12:30 - 2:30) 11/4/2019 (PM) 11/04/2019
Corrections:


Miscellaneous/Other
Carried Forward
11/04/2019
Signs, gates, and exterior lights.

Miscellaneous/Other
Comment Only
11/04/2019
Sign listings - ok Section labeling and individual.

Electrical Rough-in Inspection Partial Pass 12/2/2019 (12:30 - 2:30) 12/2/2019 (PM) 12/02/2019
Corrections:


Miscellaneous/Other
Resolved
12/02/2019
Signs, gates, and exterior lights.

Miscellaneous/Other
Comment Only
12/02/2019
Sign wiring- ok

Miscellaneous/Other
Carried Forward
12/02/2019
Still need Class 2 power supply for security gate wiring.

Electrical Final Inspection Partial Pass 12/10/2019 (12:30 - 2:30) 12/10/2019 (PM) 12/10/2019
Corrections:


Miscellaneous/Other
Carried Forward
12/10/2019
Still need Class 2 power supply for keypad controller supply.

Electrical Rough-in Inspection Passed 12/12/2019
Corrections:


Miscellaneous/Other
Resolved
12/12/2019
Still need Class 2 power supply for security gate wiring.

Electrical Final Inspection Passed 12/12/2019
Corrections:


Miscellaneous/Other
Resolved
12/12/2019
Still need Class 2 power supply for keypad controller supply.

Miscellaneous/Other
Comment Only
12/12/2019
Issues resolved. Egress lighting test- ok