Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 10/15/2018 (12:30 - 2:30) | 10/15/2018 | 10/15/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/15/2018
UG for service only.- ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/29/2018 (12:30 - 2:30) | 10/29/2018 (PM) | 10/29/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/29/2018
RI Office area only walls - ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 01/08/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
01/08/2019
Above ceiling- ok
|
||||
Electrical Rough-in Inspection | Failed | 1/17/2019 (12:30 - 2:30) | 1/17/2019 (PM) | 01/17/2019 |
Corrections:
Miscellaneous/Other
Outstanding
01/18/2019
Install bushings on 3” EMT in service.
|
||||
Miscellaneous/Other
Outstanding
01/18/2019
Install 2 ground rods and attach GEC to service.
|
||||
Miscellaneous/Other
Outstanding
01/18/2019
480/277 panel needs to have grounds and neutrals separated.
|
||||
Miscellaneous/Other
Outstanding
01/18/2019
Separately derived system needs to be bonded to GE system in building and bonded to secondary side of system. If done in panel install main bonding jumper .
|
||||
Electrical Rough-in Inspection | Passed | 01/18/2019 | ||
Corrections:
Miscellaneous/Other
Resolved
01/18/2019
Install bushings on 3” EMT in service.
|
||||
Miscellaneous/Other
Resolved
01/18/2019
Install 2 ground rods and attach GEC to service.
|
||||
Miscellaneous/Other
Resolved
01/18/2019
480/277 panel needs to have grounds and neutrals separated.
|
||||
Miscellaneous/Other
Resolved
01/18/2019
Separately derived system needs to be bonded to GE system in building and bonded to secondary side of system. If done in panel install main bonding jumper .
|
||||
Electrical Final Inspection | Partial Pass | 1/18/2019 (12:30 - 2:30) | 1/18/2019 (PM) | 01/18/2019 |
Corrections:
Miscellaneous/Other
Resolved
01/22/2019
Compressor sprinkler wiring. For completion in phase 2.
|
||||
Miscellaneous/Other
Resolved
01/22/2019
Repair ground to RTU’s
|
||||
Miscellaneous/Other
Resolved
01/22/2019
FA completion
|
||||
Miscellaneous/Other
Outstanding
01/18/2019
UG for exterior lights and gates .
|
||||
Electrical Final Inspection | Partial Pass | 1/22/2019 (8:00 - 10:00) | 1/22/2019 (AM) | 01/22/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
01/22/2019
Complete ground at water service.
|
||||
Miscellaneous/Other
Carried Forward
01/22/2019
Outside UG needs to be completed when not frozen. Assume will be spring time when completed. Temp power ran around fence area.
|
||||
Miscellaneous/Other
Comment Only
01/22/2019
Inside wiring other than outstanding issues - ok
Will allow for TCO per BO determination.
Phase 2 permits will be needed for other work being completed.
|
||||
Lighting Inspection Sign | Passed | 2/18/2019 | 02/28/2019 | |
Nick J. inspection 2.25.19 | ||||
Electrical Final Inspection | Partial Pass | 5/29/2019 (2:30 - 3:30) | 5/29/2019 (PM) | 05/29/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/29/2019
Complete ground at water service.
|
||||
Miscellaneous/Other
Resolved
05/29/2019
Outside UG needs to be completed when not frozen. Assume will be spring time when completed. Temp power ran around fence area.
|
||||
Miscellaneous/Other
Comment Only
05/29/2019
UG piping covered.
Light poles grounded- ok
|
||||
Miscellaneous/Other
Carried Forward
05/29/2019
Need to have wet location splices for all in-ground boxes.
|
||||
Electrical Final Inspection | Passed | 09/19/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/19/2019
Issues resolved.
|
||||
Electrical Final Inspection | Passed | 09/19/2019 | ||
Corrections:
Miscellaneous/Other
Outstanding
05/29/2019