Permit Application Status

PREL201810009


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL201810009
Electrical
Finaled
Nick Mauk
Repair/Replace
electrical work in the data center- install 30 0-100 amp feeder/circuits and 1 45 KVA transformer.
08/29/2018
09/13/2018
07/17/2019
01/18/2019

Locations

Permits

Permit Number: PREL201810009

Electrical
Finaled
09/13/2018
07/17/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 10/3/2018 (8:00 - 10:00) 10/3/2018 10/03/2018
Corrections:


Miscellaneous/Other
Comment Only
10/03/2018
Sever rack room- wall RI OK

Miscellaneous/Other
Outstanding
10/03/2018
Contractor to provide documentation that alternate source - generator power is an optional standby source and not life safety.

Electrical Rough-in Inspection Passed 12/3/2018 (8:00 - 10:00) 12/3/2018 (PM) 12/03/2018
Corrections:


Miscellaneous/Other
Comment Only
12/03/2018
RI OK above ceiling for power and lighting. Transformer OK

Electrical Final Inspection Passed 1/18/2019 (8:00 - 10:00) 1/18/2019 (AM) 01/18/2019