PREL201810406
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 9/28/2018 (10:00 - 12:00) | 9/28/2018 | 09/28/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/28/2018
Wall RI OK
|
||||
Electrical Rough-in Inspection | Passed | 10/18/2018 (10:00 - 12:00) | 10/18/2018 | 10/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2018
RI OK for above ceiling for power and lighting.
|
||||
Electrical Final Inspection | Partial Pass | 10/30/2018 (10:00 - 12:00) | 10/30/2018 (AM) | 10/30/2018 |
Corrections:
Miscellaneous/Other
Comment Only
12/20/2018
Final- partial pass. Partition furniture installation not ready. All electrical connection to be made by a licensed electrical contractor.
Remove cord above ceiling at projection equipment. Call for final.
|
||||
Electrical Final Inspection | Passed | 12/20/2018 (10:00 - 12:00) | 12/20/2018 (AM) | 12/20/2018 |
Corrections:
Miscellaneous/Other
Outstanding
10/30/2018
Final- partial pass. Partition furniture installation not ready. All electrical connection to be made by a licensed electrical contractor.
Remove cord above ceiling at projection equipment. Call for final.
|