PREL201810908
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 11/6/2019 (12:30 - 2:30) | 12/12/2018 | |
Corrections:
Miscellaneous/Other
Comment Only
12/12/2018
Questions at site.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/4/2019 (8:00 - 10:00) | 6/4/2019 (AM) | 06/05/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/05/2019
4000 AMP 3 Phase 120/208 volt service OK
to release to Xcel.
|
||||
Miscellaneous/Other
Carried Forward
06/05/2019
All required clearance and egress to be reviewed and inspected at subsequent inspections.
|
||||
Electrical Rough-in Inspection | Partial Pass | 6/13/2019 (8:00 - 10:00) | 6/13/2019 (AM) | 06/13/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
06/13/2019
All required clearance and egress to be reviewed and inspected at subsequent inspections.
|
||||
Miscellaneous/Other
Comment Only
06/13/2019
Progress inspection- review of preliminary RI of units
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/11/2019 (10:00 - 12:00) | 7/11/2019 (AM) | 07/11/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
07/11/2019
All required clearance and egress to be reviewed and inspected at subsequent inspections.
|
||||
Miscellaneous/Other
Comment Only
07/11/2019
Bond conductor at one wet niche luminarie
OK.
Verify if any metallic cup/anchors are to be installed- call for additional inspections as needed.
|
||||
Miscellaneous/Other
Comment Only
07/11/2019
RI OK at 5th floor units for power and lighting.
|
||||
Miscellaneous/Other
Carried Forward
07/11/2019
Verify who is responsible for temperature control
wiring.
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/23/2019 (10:00 - 12:00) | 7/23/2019 (AM) | 07/23/2019 |
Corrections:
Miscellaneous/Other
Outstanding
07/11/2019
All required clearance and egress to be reviewed and inspected at subsequent inspections.
|
||||
Miscellaneous/Other
Resolved
07/23/2019
Verify who is responsible for temperature control
wiring.
|
||||
Miscellaneous/Other
Comment Only
07/23/2019
5 th floor stat wiring - ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 7/25/2019 (12:30 - 2:30) | 7/25/2019 (PM) | 07/25/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/25/2019
4th floor stat wiring - ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/6/2019 (12:30 - 2:30) | 8/6/2019 (PM) | 08/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/06/2019
Questions at site in regards to egress lighting requirements.
RI - 3rd Floor units OK.
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/19/2019 (12:30 - 2:30) | 8/19/2019 (PM) | 08/19/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/19/2019
2nd floor units -RI OK.
Corridors at hard lids OK- check when whip is installed.
Partial view at trenching at bollard lighting at building exterior
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/26/2019 (10:00 - 12:00) | 8/26/2019 (AM) | 08/26/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/26/2019
1st level- kitchen- wall RI OK.
1st floor 3- units RI OK.
|
||||
Miscellaneous/Other
Carried Forward
08/26/2019
Inspector note:
1. Receptacle outlet for mirror in bathrooms requires AFCI/GFCI protection- must be readily accessible.
2. Bathroom receptacle circuit requires AFCI protection.
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/6/2019 (8:00 - 10:00) | 9/6/2019 (AM) | 09/06/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
09/06/2019
Inspector note:
1. Receptacle outlet for mirror in bathrooms requires AFCI/GFCI protection- must be readily accessible.
2. Bathroom receptacle circuit requires AFCI protection.
|
||||
Miscellaneous/Other
Comment Only
09/06/2019
Bonding inspection- OK
No rebar in pool deck- # 8 copper ring around pool deck, 4 corners of the rebar at pool shell,
connection to wet niche luminaire, one cup and handicap access all OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/19/2019 (12:30 - 2:30) | 9/19/2019 (PM) | 09/19/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/19/2019
Inspector note:
1. Receptacle outlet for mirror in bathrooms requires AFCI/GFCI protection- must be readily accessible.
2. Bathroom receptacle circuit requires AFCI protection.
|
||||
Miscellaneous/Other
Comment Only
09/19/2019
First floor offices, bathrooms and common area wall RI- OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/10/2019 (8:00 - 10:00) | 10/10/2019 (AM) | 10/10/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/10/2019
1st Level East wing- RI OK at, Back wall bar, main public restrooms -walls and ceiling, guest laundry, boardroom walls & ceiling, Guest room suites, main laundry walls, bathroom wall, fitness center walls & ceiling and office area walls
|
||||
Miscellaneous/Other
Comment Only
10/10/2019
1st Level East wing- RI OK at, Back wall bar, main public restrooms -walls and ceiling, guest laundry, boardroom walls & ceiling, Guest room suites, main laundry walls, bathroom wall, fitness center walls & ceiling and office area walls
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/23/2019 (8:00 - 10:00) | 10/23/2019 (AM) | 10/23/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/23/2019
Wall RI OK at meeting rooms and NE back of house areas
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/30/2019 (12:30 - 2:30) | 10/30/2019 (PM) | 10/30/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/30/2019
Questions at site
|
||||
Electrical Rough-in Inspection | Partial Pass | 10/31/2019 (12:30 - 2:30) | 10/31/2019 (PM) | 10/31/2019 |
Electrical Rough-in Inspection | Partial Pass | 11/1/2019 (12:30 - 2:30) | 11/1/2019 (PM) | 11/01/2019 |
Corrections:
Miscellaneous/Other
Outstanding
11/01/2019
Verify listing of modular power outlets at furniture and listing and approval of furniture provided luminarie at clothes pole
|
||||
Miscellaneous/Other
Comment Only
11/01/2019
Verify listing of modular power outlets at furniture and listing and approval of furniture provided luminarie at clothes pole
|
||||
Miscellaneous/Other
Comment Only
11/01/2019
Hard lid at pool area OK
|
||||
Miscellaneous/Other
Comment Only
11/01/2019
Plug check at units 531-545 and 526-544- verify AFCI/ panels locked
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/4/2019 (12:30 - 2:30) | 11/4/2019 (PM) | 11/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/04/2019
5th units - final OK except 524 not ready.
Check AFCI at next inspection
|
||||
Miscellaneous/Other
Comment Only
11/04/2019
Hard lid OK at first level corridor
|
||||
Electrical Final Inspection | Partial Pass | 11/6/2019 (12:30 - 2:30) | 11/6/2019 (PM) | 11/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/06/2019
Spot checks / plug check units #426 through # 447. Some devices/ receptacles taped off for paint/wallpaper-
Unable to check. Unit #424 not ready
|
||||
Electrical Final Inspection | Partial Pass | 11/7/2019 (12:30 - 2:30) | 11/7/2019 (PM) | 11/07/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/07/2019
Units OK at #401 through #422. Some areas spot checks only- devices taped
over for finishing.
Note no receptacle outlet power in #408.
|
||||
Miscellaneous/Other
Comment Only
11/07/2019
OK to
Cover/pad upper level corridors
|
||||
Electrical Final Inspection | Partial Pass | 11/14/2019 (12:30 - 2:30) | 11/14/2019 (PM) | 11/14/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/14/2019
Unit final Ok at 4th floor for plug test-
except unit 424 and 408- no power
|
||||
Electrical Final Inspection | Partial Pass | 11/15/2019 (12:30 - 2:30) | 11/15/2019 (PM) | 11/15/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/15/2019
1st level common area above ceiling partial RI OK
|
||||
Miscellaneous/Other
Comment Only
11/15/2019
3rd floor units- spot checks for plug check
Some areas devices are taped off for paint/wallpaper finishes- no access.
Unit 324 no power
Units 326 through 346 and 331 through 347 OK as noted.
All tests of AFCI or GFCI protection at panelboards to be at subsequent inspection
|
||||
Electrical Final Inspection | Partial Pass | 11/18/2019 (8:00 - 10:00) | 11/18/2019 (AM) | 11/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/18/2019
Plug checks on 3rd floor units- # 301- #322
3rd floor complete for plug checks of units...spot checking as unable to access all openings.
|
||||
Electrical Final Inspection | Partial Pass | 11/19/2019 (10:00 - 12:00) | 11/19/2019 (AM) | 11/19/2019 |
Corrections:
Miscellaneous/Other
Outstanding
11/19/2019
Routine walkthrough of units- sent email to contractor and general contractor in relation to NRTL listing and labeling requirements of modular power and luminaires in built in furniture.
|
||||
Electrical Final Inspection | Partial Pass | 11/20/2019 (10:00 - 12:00) | 11/20/2019 (AM) | 11/21/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/21/2019
Site visit only
|
||||
Electrical Final Inspection | Partial Pass | 11/21/2019 (10:00 - 12:00) | 11/21/2019 (AM) | 11/21/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/21/2019
Progress inspection only
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/25/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/25/2019
Rooftop HVAC equipment - electrical OK
|
||||
Electrical Final Inspection | Partial Pass | 12/10/2019 (8:00 - 10:00) | 12/10/2019 (AM) | 12/10/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/10/2019
Met contractor onsite- AFCI and GFCI testing at panelboards for all units 5th floor, 4th floor, 3rd floor & 2nd floor all OK.
|
||||
Electrical Final Inspection | Partial Pass | 12/12/2019 (8:00 - 10:00) | 12/12/2019 (AM) | 12/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/12/2019
Plug checks at 2nd floor units -OK
|
||||
Electrical Final Inspection | Partial Pass | 12/13/2019 (8:00 - 10:00) | 12/13/2019 (AM) | 12/13/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/13/2019
Above drop ceiling at kitchen, engineer office and break room.
|
||||
Electrical Final Inspection | Partial Pass | 12/16/2019 (8:00 - 10:00) | 12/16/2019 (AM) | 12/16/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/16/2019
Progress inspection
|
||||
Electrical Final Inspection | Partial Pass | 12/17/2019 (8:00 - 10:00) | 12/17/2019 (AM) | 12/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/17/2019
Progress inspection
|
||||
Electrical Final Inspection | Partial Pass | 12/20/2019 (8:00 - 10:00) | 12/20/2019 (AM) | 12/20/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/20/2019
Walk through with contractor-
Water room OK, laundry room equipment and disconnect means OK.
Above ceilings at common areas and offices- OK.
Elevator disconnect room OK.
Kitchen cooler equipment OK.
MUA unit visual OK.
|
||||
Electrical Final Inspection | Partial Pass | 1/7/2020 (8:00 - 10:00) | 1/7/2020 (AM) | 01/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/07/2020
site visit only- questions at site.
|
||||
Electrical Final Inspection | Partial Pass | 1/10/2020 (8:00 - 10:00) | 1/10/2020 (AM) | 01/14/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/14/2020
signs OK
|
||||
Miscellaneous/Other
Carried Forward
01/14/2020
Walk through OK
|
||||
Electrical Final Inspection | Partial Pass | 1/21/2020 (12:30 - 2:30) | 1/21/2020 (PM) | 01/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/23/2020
Walk through OK- Partial final
Minor work left at pool and main lobby
|
||||
Electrical Rough-in Inspection | Passed | 01/30/2020 | ||
Electrical Rough-in Inspection | Passed | 01/30/2020 | ||
Electrical Final Inspection | Passed | 01/30/2020 |