Summary

PREL201811247
Electrical
Finaled
Nick Mauk
Alteration/Remodel
JOB 83506 POLAR SEMI SUBSTATION 3 In P3 Main Electrical room: • Rig and place the three (3) new sections of S&C switchgear to the Northwest corner of the room on the existing housekeeping pad. Assemble per manufacturer’s instructions. Connect the 13.8kV circuit from the Bay 1 tap box in the main gear to the Bay3 tap box in the expansion gear using existing conduit routed below floor with 3- 4/0, 1 #4G, CU, 15kV, EPR, lead free, 133%, MV-105, tape shield Southwire spec 46302, alternate vendors include Aetna Insulated Wire, Inc., General Cable Technologies Corp., Okonite Company, Prysmian Cables and Systems. o Termination kits shall be 3M Cold Shrink QT-III series. Provide six (6) spare sets of termination kits. o The 13.8kV conductors shall be acceptance tested with VLF AC withstand testing per the manufacturers recommendations. In P3 Upper Mechanical Area, place the components of Substation #3 on housekeeping pads, this would include the Medium Voltage Main Switch, 4000kVA dry transformer and mating 480V panelboards. This will also include the 480V / 208Y 500Kva transformer w/Main, as well as the 208Y / 1600A distribution panel and the 480V / 800A distribution panel, assemble per manufacturer’s instructions. Extend the 13.8kV 150A feeder conduit from its current location at floor level on the North side of the first floor Phase2 expansion cleanroom area and extend feeder conduit up (~32 feet) to the Upper Mechanical Level and route to the location of the new Substation #3, Medium Voltage Disconnect Main switch. From the new S&C gear in the Northwest corner of the main electrical room, BAY1: Provide a 13.8kV feeder to the unit substation Medium Voltage Disconnect switch. a. Conductors shall be #1/0, CU, 15kV, EPR, lead free, 133%, MV-105, tape shield Southwire spec 46302 or approved equivalent (alternate suppliers mentioned above). b. Conduit for 13.8kV feeder shall be painted red and labeled “HIGH VOLTAGE”. Lettering height shall be approximately 25% of the circumference of the conduit. Labels shall be in each room the conduit passes through and shall not exceed 50’ spacing between labels. • Extend the 13.8kV conduit from its current location at floor level on the South side of the first floor Phase 1 cleanroom, up the wall ~10’ to a future tap box (provided). o Provide 13.8kV feeder from new S&C gear in the Northwest corner of the main electrical room, BAY2 to the tap box added above, conductors to follow same specification above.From Substation#3 run circuits to locations for: • One (1) 480V / 800A circuit to the main inlet on the 208Y 500kVA transformer w/Main. • Connect the output of the 500kVA 208V transformer to the 1600A distribution panelboard. • One (1) 480V / 800A circuit to the inlet of the 480V / 800A distribution panelboard.
09/21/2018
10/08/2018
06/28/2020
12/31/2019

Locations

Permits

Permit Number: PREL201811247

Electrical
Finaled
10/08/2018
06/28/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Passed 10/17/2018 (10:00 - 12:00) 10/17/2018 10/17/2018
Corrections:


Miscellaneous/Other
Comment Only
10/17/2018
Progress inspection OK Contractor to provide documentation of all GFPE tests.

Electrical Final Inspection Partial Pass 12/4/2018 (10:00 - 12:00) 12/4/2018 (AM) 12/04/2018
Corrections:


Miscellaneous/Other
Carried Forward
12/04/2018
Progress inspection and walk through with contractor OK.

Miscellaneous/Other
Comment Only
12/04/2018
Progress inspection and walk through with contractor OK.

Miscellaneous/Other
Carried Forward
12/04/2018
Provide GFPE testing documentation. Provide riser diagram- with conductor sizing, and available fault current at equipment. Verify energy reduction per 240.87

Electrical Final Inspection Passed 12/30/2019 (12:30 - 2:30) 12/30/2019 (PM) 12/31/2019
Corrections:


Miscellaneous/Other
Comment Only
12/31/2019
Progress inspection and walk through with contractor OK.

Miscellaneous/Other
Resolved
12/31/2019
Provide GFPE testing documentation. Provide riser diagram- with conductor sizing, and available fault current at equipment. Verify energy reduction per 240.87