PREL201902483
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
04/15/2019
Partial pass- lighting in dining OK
Spoke to GC- all limited energy wiring requires independent support- all abandoned to be demolished. Advised GC not to pad until issue is addressed.
|
||||
Electrical Final Inspection | Pending | |||
Electrical Rough-in Inspection | Partial Pass | 4/1/2019 (8:00 - 10:00) | 4/1/2019 (AM) | 04/01/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/01/2019
Wall RI only- ok
Hard ceiling RI- ok
UG- ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/9/2019 (8:00 - 10:00) | 4/9/2019 (AM) | 04/09/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/09/2019
Above ceiling in bathrooms - ok
|
||||
Electrical Rough-in Inspection | Partial Pass | 4/15/2019 (12:30 - 2:30) | 4/15/2019 (PM) | 04/15/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
04/15/2019
Partial pass- lighting in dining OK
Spoke to GC- all limited energy wiring requires independent support- all abandoned to be demolished. Advised GC not to pad until issue is addressed.
|
||||
Electrical Final Inspection | Partial Pass | 4/19/2019 (10:00 - 12:00) | 4/19/2019 (AM) | 04/19/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2019
Interior only final - ok
Egress lighting - ok
|