Summary

PREL201902606
Electrical
Finaled
MOAC MALL HOLDINGS LLC
Other
GROUND GENERATORS AND RUN POWER FOR INTER-SPORT 3X3 BASKETBALL TOURNAMENT EVENT ON THE SOUTH SIDE ON MALL OF AMERICA. GENERATORS TO FEED PRODUCTION TRUCK.
03/26/2019
03/27/2019
09/30/2019
04/03/2019

Locations

Permits

Permit Number: PREL201902606

Electrical
Finaled
03/27/2019
09/30/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Final Inspection Passed 4/3/2019 (12:30 - 2:30) 4/3/2019 (PM) 04/03/2019
Corrections:


Miscellaneous/Other
Comment Only
04/03/2019
Grounding electrode conductor connection to generator equipment only.