PREL201903486
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 4/25/2019 (8:00 - 10:00) | 4/25/2019 (AM) | 04/25/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2019
800 amp 480 volt feeder ok to 500 KVA transformer and 1600 amp distribution.
|
||||
Electrical Final Inspection | Passed w/ Conditions | 8/8/2019 (2:30 - 3:30) | 8/8/2019 (PM) | 08/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/12/2019
Visual OK at distribution. Limited view and access at clean room.
|