PREL201903494
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 7/31/2019 (10:00 - 12:00) | 7/31/2019 (AM) | 07/31/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
07/31/2019
Wall RI phase l of 7
Need sign off sheet
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/14/2019 (10:00 - 12:00) | 8/14/2019 (AM) | 08/14/2019 |
Corrections:
Miscellaneous/Other
Resolved
08/14/2019
Wall RI phase l of 7
Need sign off sheet
|
||||
Miscellaneous/Other
Comment Only
08/14/2019
Above ceiling- ok phase 1
|
||||
Miscellaneous/Other
Comment Only
08/14/2019
Above ceiling- ok phase 1
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/6/2019 (8:00 - 10:00) | 9/6/2019 (AM) | 09/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/06/2019
Above ceiling and Wall RI - ok
Phase 2
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/24/2019 (10:00 - 12:00) | 9/24/2019 (AM) | 09/24/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/24/2019
Phase 2 final- ok
|
||||
Electrical Rough-in Inspection | Passed | 10/31/2019 (8:00 - 10:00) | 10/31/2019 (AM) | 10/31/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/31/2019
Wall RI phase 4- ok
|
||||
Electrical Final Inspection | Partial Pass | 12/3/2019 (8:00 - 10:00) | 12/3/2019 (AM) | 12/03/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/03/2019
Phase wall and above ceiling- ok
|
||||
Electrical Final Inspection | Passed | 1/17/2020 (8:00 - 10:00) | 1/17/2020 (AM) | 01/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2020
Final- ok
|