PREL201903583
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Failed | 05/02/2019 | ||
Corrections:
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified
Carried Forward
05/02/2019
All electrical equipment, machines or apparatus are required to be National Recognized Testing Laboratory certified/listed/labeled- NRTL certified. Lighting power supply is not listed.
Verify Class 2 power source and provide independent third party evaluation.
|
||||
Miscellaneous/Other
Comment Only
05/02/2019
Site visit and questions at site. Progress inspection only.
|
||||
Miscellaneous/Other
Carried Forward
05/02/2019
Provide documentation on installation of luminaries in soffits.
|
||||
Electrical Final Inspection | Partial Pass | 9/24/2019 (2:30 - 3:30) | 9/24/2019 (PM) | 09/24/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/24/2019
Met contractor on site.
Independent 3rd party evaluations provided for unlisted equipment- OK.
|
||||
Miscellaneous/Other
Comment Only
03/18/2020
Verify Class 2 source for door strike power.
|
||||
Electrical Final Inspection | Passed w/ Conditions | 09/27/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/27/2019
Verify Class 2 source for door strike power.
|