PREL201906967
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 7/29/2019 (10:00 - 12:00) | 7/29/2019 (AM) | 07/29/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
07/29/2019
Meeting on site panel and transformer clearance, one wall RI
|
||||
Electrical Rough-in Inspection | Partial Pass | 8/16/2019 (10:00 - 12:00) | 8/16/2019 (AM) | 08/16/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/16/2019
Meeting on site panel and transformer clearance, one wall RI
|
||||
Miscellaneous/Other
Comment Only
08/16/2019
RI OK at walls and hard lid ceiling
|
||||
Electrical Final Inspection | Passed w/ Conditions | 9/12/2019 (10:00 - 12:00) | 9/12/2019 (AM) | 09/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/12/2019
Final OK. Verbal to contractor onsite:
install breaker lock on for egress circuit.
Replace EMT sleeve for GEC with PVC.
Install KO seal at large J-box above the panel.
|