PREL201909945
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
10/22/2019
Sign letters have listing labels. This is not a section label. As such- the power supply is field installed and not part of the sign listing. See NEC 600.24 - the Class 2 power supply shall be listed for use with electric signs. The power supply installed is a recognized component only.
Call for re-inspection.
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/11/2019 (10:00 - 12:00) | 9/11/2019 (AM) | 09/11/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/11/2019
Wall RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/17/2019 (2:30 - 3:30) | 9/17/2019 (PM) | 09/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/17/2019
Front of house- hard lid ceiling RI OK
|
||||
Electrical Rough-in Inspection | Partial Pass | 9/20/2019 (8:00 - 10:00) | 9/20/2019 (AM) | 09/20/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/20/2019
Above ceiling RI OK at front of store
|
||||
Electrical Rough-in Inspection | Passed | 10/08/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/08/2019
South 148. Meet contractor onsite to discuss listing and labeling requirements.
|
||||
Electrical Final Inspection | Failed | 10/22/2019 (2:30 - 3:30) | 10/22/2019 (PM) | 10/22/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/22/2019
Final- partial pass only. 20 days to repair correction for sign power supply.
|
||||
Miscellaneous/Other
Carried Forward
10/22/2019
Sign letters have listing labels. This is not a section label. As such- the power supply is field installed and not part of the sign listing. See NEC 600.24 - the Class 2 power supply shall be listed for use with electric signs. The power supply installed is a recognized component only.
Call for re-inspection.
|