PREL201910446
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 9/10/2019 (12:30 - 2:30) | 9/10/2019 (PM) | 09/10/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/10/2019
Wall RI OK
|
||||
Electrical Rough-in Inspection | Passed | 9/30/2019 (12:30 - 2:30) | 9/30/2019 (PM) | 09/30/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/30/2019
RI above ceiling OK at front soffit
|
||||
Electrical Final Inspection | Not Ready | 11/7/2019 (8:00 - 10:00) | 11/7/2019 (AM) | 11/07/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
11/08/2019
Not ready for final. Complete transformer grounding and bonding.
Replace power supply for LED lighting- not Class 2 as installed.
Complete the sign installation and verify listing and disconnect means.
Provide lock on for EM light circuit.
|
||||
Building Final Inspection | VOID | 11/08/2019 | ||
Electrical Final Inspection | Passed w/ Conditions | 11/13/2019 (10:00 - 12:00) | 11/13/2019 (AM) | 11/13/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/13/2019
Not ready for final. Complete transformer grounding and bonding.
Replace power supply for LED lighting- not Class 2 as installed.
Complete the sign installation and verify listing and disconnect means.
Provide lock on for EM light circuit.
|
||||
Miscellaneous/Other
Comment Only
11/13/2019
Contractor to email pictures of the transformer bond/ground- send to Tmiller@bloomingtonmn.gov
|