PREL201911189
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Rough-in Inspection | Partial Pass | 10/30/2019 (8:00 - 10:00) | 10/30/2019 (AM) | 10/30/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
10/30/2019
Contractor to confirm with owner/governing authority as to how portions of the facility are used and licensed as it relates to NEC 517.10 (A) and (B).
Areas identified as "treatment" on building permit plan set. Electrical is design -build.
Contractor is proceeding at own risk per discussion 10/30/2019 with PM Brad.
Wall RI OK for installation methods/ strapping and securing of wiring methods.
If NEC 517 applies- then RI would need to changed to comply with 517.13.
Area inspected is partial pass for east area walls.
|
||||
Electrical Rough-in Inspection | Partial Pass | 11/6/2019 (8:00 - 10:00) | 11/6/2019 (AM) | 11/06/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
11/06/2019
Contractor to confirm with owner/governing authority as to how portions of the facility are used and licensed as it relates to NEC 517.10 (A) and (B).
Areas identified as "treatment" on building permit plan set. Electrical is design -build.
Contractor is proceeding at own risk per discussion 10/30/2019 with PM Brad.
Wall RI OK for installation methods/ strapping and securing of wiring methods.
If NEC 517 applies- then RI would need to changed to comply with 517.13.
Area inspected is partial pass for east area walls.
|
||||
Miscellaneous/Other
Comment Only
11/06/2019
Wall RI- part pass. Call for wall RI for remainder of walls not complete at this inspection
|
||||
Electrical Rough-in Inspection | Partial Pass | 12/9/2019 (8:00 - 10:00) | 12/9/2019 (AM) | 12/09/2019 |
Corrections:
Miscellaneous/Other
Resolved
12/09/2019
Contractor to confirm with owner/governing authority as to how portions of the facility are used and licensed as it relates to NEC 517.10 (A) and (B).
Areas identified as "treatment" on building permit plan set. Electrical is design -build.
Contractor is proceeding at own risk per discussion 10/30/2019 with PM Brad.
Wall RI OK for installation methods/ strapping and securing of wiring methods.
If NEC 517 applies- then RI would need to changed to comply with 517.13.
Area inspected is partial pass for east area walls.
|
||||
Miscellaneous/Other
Comment Only
12/09/2019
Spoke to GC- all electrical subcontractors to contact electrical inspector- temperature control and fire alarm wiring requires permits and inspections
|
||||
Miscellaneous/Other
Comment Only
12/09/2019
Partial pass- East section RI OK above ceilings for power and lighting
|
||||
Electrical Rough-in Inspection | Passed | 12/23/2019 (12:30 - 2:30) | 12/23/2019 (PM) | 12/23/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/23/2019
Above ceiling RI OK
|
||||
Electrical Final Inspection | Partial Pass | 12/31/2019 (8:00 - 10:00) | 12/31/2019 (AM) | 12/31/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/31/2019
Partial pass for final. EM function OK.
Minor installations to complete.
|
||||
Electrical Final Inspection | Passed | 1/3/2020 (8:00 - 10:00) | 1/3/2020 (AM) | 01/03/2020 |
Hased project Phase 1 completed on 1/03/2020. jsmidt 01/15/2020 2:09 PM | ||||
Electrical Rough-in Inspection | Partial Pass | 1/17/2020 (12:30 - 2:30) | 1/17/2020 (PM) | 01/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2020
Minor wall RI for Phase 2 - ok
|
||||
Electrical Rough-in Inspection | Failed | 1/31/2020 (8:00 - 10:00) | 1/31/2020 (AM) | 01/31/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
01/31/2020
NM cable needs to be removed from ceiling space
|
||||
Miscellaneous/Other
Comment Only
01/31/2020
Partial ceiling- ok
General needs FA and Temp control permits and inspections before padding ceiling.
|
||||
Electrical Rough-in Inspection | Partial Pass | 2/24/2020 (8:00 - 10:00) | 2/24/2020 (AM) | 02/24/2020 |
Corrections:
Miscellaneous/Other
Resolved
02/24/2020
NM cable needs to be removed from ceiling space
|
||||
Miscellaneous/Other
Comment Only
02/24/2020
This is a phased project- final OK for phase 2 OK. Call for Rough-in inspections as required or needed for phase 3.
|
||||
Electrical Rough-in Inspection | Partial Pass | 3/13/2020 (8:00 - 10:00) | 3/13/2020 (AM) | 03/13/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
03/13/2020
Spoke to building tenant owner: all abandoned low voltage cable to be demolished.
All non plenum temperature control wiring to be replaced- temperature control wiring requires electrical permit and electrical inspection.
Maintain independent support of all voice and data cabling-for relocation: licensed contractor only
|
||||
Miscellaneous/Other
Comment Only
03/13/2020
RI above ceiling for power and lighting at phase 3 East open office
|
||||
Electrical Final Inspection | Passed | 4/9/2020 (2:30 - 3:30) | 4/9/2020 (PM) | 04/09/2020 |
Corrections:
Miscellaneous/Other
Resolved
04/09/2020
Spoke to building tenant owner: all abandoned low voltage cable to be demolished.
All non plenum temperature control wiring to be replaced- temperature control wiring requires electrical permit and electrical inspection.
Maintain independent support of all voice and data cabling-for relocation: licensed contractor only
|
||||
Miscellaneous/Other
Comment Only
04/09/2020
Final OK for all phases covered under this permit number.
|