PREL201911387
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Electrical Final Inspection | Passed | 10/16/2019 (8:00 - 10:00) | 10/16/2019 (AM) | 10/16/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/16/2019
Limited view and access. Met contractor on site for walk through.
Building automation work at kitchens for fan speed controls- visual OK.
No testing performed at inspection.
Contractor provided verbal verification of safety systems check prior to inspection
|