PREL201911567
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Final Inspection | Pending | |||
|
Corrections:
Miscellaneous/Other
Outstanding
10/15/2019
Need to meet contractor on site
|
||||
| Electrical Final Inspection | Not Ready | 10/15/2019 (8:00 - 10:00) | 10/15/2019 (AM) | 10/15/2019 |
|
Corrections:
Miscellaneous/Other
Carried Forward
10/15/2019
Need to meet contractor on site
|
||||
| Lighting Inspection | Passed | 10/26/2019 | ||