Permit Application Status

PREL201914824


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL201914824
Electrical
Expired
KNOX & AMERICAN I LLC
Other
Complete electrical systems for 125-unit apartment building, including wiring for temp control and fire alarm
12/11/2019
01/06/2020
10/30/2021

Locations

Property
0402724240006

1901 W 80TH 1/2 St, Bloomington, MN 55431

Permits

Permit Number: PREL201914824

Electrical
Expired

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Pending
Electrical Final Inspection Pending
Miscellaneous/Other
Outstanding
05/03/2021
Available fault current needed for sub panels and metering areas.

Miscellaneous/Other
Outstanding
05/03/2021
Single receptacles needed for no GFCI sumps according to elevator inspection.

Miscellaneous/Other
Outstanding
05/03/2021
Close up fire pit area if not completed at next inspection.

Electrical Rough-in Inspection Partial Pass 4/27/2020 (Morning) 4/27/2020 (AM) 04/27/2020
Miscellaneous/Other
Comment Only
04/27/2020
Partial- UG and trench progress inspection OK

Electrical Rough-in Inspection Partial Pass 9/3/2020 (10:00 - 12:00) 9/3/2020 (AM) 09/03/2020
Miscellaneous/Other
Comment Only
09/03/2020
RI 4th floor west- ok

Electrical Rough-in Inspection Partial Pass 9/10/2020 (10:00 - 12:00) 9/10/2020 (AM) 09/10/2020
Miscellaneous/Other
Comment Only
09/10/2020
4th floor RI East half - ok

Electrical Rough-in Inspection Partial Pass 9/17/2020 (10:00 - 12:00) 9/17/2020 (AM) 09/17/2020
Miscellaneous/Other
Comment Only
09/17/2020
3rd floor west RI- ok

Electrical Rough-in Inspection Partial Pass 9/23/2020 (8:00 - 10:00) 9/23/2020 (AM) 09/23/2020
Miscellaneous/Other
Comment Only
09/23/2020
Room RI, 3rd floor east side of building- ok

Electrical Rough-in Inspection Passed 10/1/2020 (10:00 - 12:00) 10/1/2020 (AM) 10/01/2020
Miscellaneous/Other
Comment Only
10/01/2020
Ri 2nd floor west side - ok

Electrical Rough-in Inspection Partial Pass 10/8/2020 (10:00 - 12:00) 10/8/2020 (AM) 10/08/2020
Miscellaneous/Other
Comment Only
10/08/2020
2nd floor RI middle section- ok

Electrical Rough-in Inspection Partial Pass 10/15/2020 (10:00 - 12:00) 10/15/2020 (AM) 10/15/2020
Miscellaneous/Other
Comment Only
10/15/2020
2nd floor East RI- ok

Electrical Rough-in Inspection Partial Pass 10/22/2020 (10:00 - 12:00) 10/22/2020 (AM) 10/22/2020
Miscellaneous/Other
Comment Only
10/22/2020
RI 1st floor west- ok

Electrical Rough-in Inspection Partial Pass 10/29/2020 (10:00 - 12:00) 10/29/2020 (AM) 10/29/2020
Miscellaneous/Other
Comment Only
10/29/2020
RI 1st floor center and common area- ok

Electrical Rough-in Inspection Partial Pass 11/5/2020 (10:00 - 12:00) 11/5/2020 (AM) 11/05/2020
Miscellaneous/Other
Comment Only
11/05/2020
1st floor RI units on east side of building.

Electrical Rough-in Inspection Partial Pass 11/18/2020 (10:00 - 12:00) 11/18/2020 (AM) 11/19/2020
Miscellaneous/Other
Comment Only
11/19/2020
Service inspection only- ok Xcel contacted

Lighting Inspection Sign Passed 1/11/2021 01/06/2021
Electrical Final Inspection Partial Pass 2/23/2021 (10:00 - 12:00) 2/23/2021 (AM) 02/23/2021
Miscellaneous/Other
Comment Only
02/23/2021
4th and 3rd floor finals west side - ok

Electrical Final Inspection Partial Pass 3/3/2021 (8:00 - 10:00) 3/3/2021 (AM) 03/03/2021
Miscellaneous/Other
Comment Only
03/03/2021
4th and 3rd floor finals west side- ok

Electrical Final Inspection Partial Pass 3/9/2021 (12:30 - 2:30) 3/9/2021 (PM) 03/09/2021
Miscellaneous/Other
Comment Only
03/09/2021
2nd floor finals west and middle areas

Electrical Final Inspection Partial Pass 3/24/2021 (8:00 - 10:00) 3/24/2021 (AM) 03/24/2021
Miscellaneous/Other
Comment Only
03/24/2021
Unit finals for East half 2nd floor and 1st floor.

Electrical Final Inspection Partial Pass 4/19/2021 (10:00 - 12:00) 4/19/2021 (AM) 04/19/2021
Miscellaneous/Other
Comment Only
04/19/2021
1st floor unit finals- ok

Electrical Final Inspection Partial Pass 5/3/2021 (12:30 - 2:30) 5/3/2021 (PM) 05/03/2021
Miscellaneous/Other
Carried Forward
05/03/2021
Available fault current needed for sub panels and metering areas.

Miscellaneous/Other
Carried Forward
05/03/2021
Single receptacles needed for no GFCI sumps according to elevator inspection.

Miscellaneous/Other
Carried Forward
05/03/2021
Close up fire pit area if not completed at next inspection.