Permit Application Status

PREL202000689


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL202000689
Electrical
Finaled
LIFESPACE COMMUNITIES INC
Other
New Residential Living Building (93 Units)
01/24/2020
01/28/2020
03/12/2022
09/13/2021

Locations

Permits

Permit Number: PREL202000689

Electrical
Finaled
01/28/2020
03/12/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Electrical Rough-in Inspection Partial Pass 4/16/2020 (12:30 - 2:30) 4/16/2020 (PM) 04/16/2020
Corrections:


Miscellaneous/Other
Carried Forward
04/16/2020
Underground residential building

Electrical Rough-in Inspection Partial Pass 9/2/2020 (8:00 - 10:00) 9/2/2020 (AM) 09/02/2020
Corrections:


Miscellaneous/Other
Carried Forward
09/02/2020
Underground residential building

Miscellaneous/Other
Comment Only
09/02/2020
East side of building UG service pipes- ok

Electrical Rough-in Inspection Partial Pass 11/13/2020 (12:30 - 2:30) 11/13/2020 (PM) 11/13/2020
Corrections:


Miscellaneous/Other
Carried Forward
11/13/2020
Underground residential building

Miscellaneous/Other
Carried Forward
11/13/2020
5th floor partial ri

Electrical Rough-in Inspection Partial Pass 12/4/2020 (8:00 - 10:00) 12/4/2020 (AM) 12/04/2020
Corrections:


Miscellaneous/Other
Carried Forward
12/04/2020
Underground residential building

Miscellaneous/Other
Carried Forward
12/04/2020
5th floor partial ri

Miscellaneous/Other
Carried Forward
12/04/2020
4th floor unit ri

Electrical Rough-in Inspection Partial Pass 12/11/2020 (8:00 - 10:00) 12/11/2020 (AM) 12/11/2020
Corrections:


Miscellaneous/Other
Carried Forward
12/11/2020
Underground residential building

Miscellaneous/Other
Carried Forward
12/11/2020
5th floor partial ri

Miscellaneous/Other
Carried Forward
12/11/2020
4th floor unit ri

Miscellaneous/Other
Carried Forward
12/11/2020
5th, 4th, 3rd floor halls partial ri

Electrical Rough-in Inspection Partial Pass 12/21/2020 (8:00 - 10:00) 12/21/2020 (AM) 12/21/2020
Corrections:


Miscellaneous/Other
Carried Forward
12/21/2020
Underground residential building

Miscellaneous/Other
Carried Forward
12/21/2020
5th floor partial ri

Miscellaneous/Other
Carried Forward
12/21/2020
4th floor unit ri

Miscellaneous/Other
Carried Forward
12/21/2020
5th, 4th, 3rd floor halls partial ri

Miscellaneous/Other
Carried Forward
12/21/2020
3rd floor partial ri

Electrical Rough-in Inspection Partial Pass 12/31/2020 (8:00 - 10:00) 12/31/2020 (AM) 12/31/2020
Corrections:


Miscellaneous/Other
Carried Forward
12/31/2020
Underground residential building

Miscellaneous/Other
Carried Forward
12/31/2020
5th floor partial ri

Miscellaneous/Other
Carried Forward
12/31/2020
4th floor unit ri

Miscellaneous/Other
Carried Forward
12/31/2020
5th, 4th, 3rd floor halls partial ri

Miscellaneous/Other
Carried Forward
12/31/2020
3rd floor partial ri

Miscellaneous/Other
Carried Forward
12/31/2020
3rd floor west final

Electrical Rough-in Inspection Partial Pass 1/11/2021 (8:00 - 10:00) 1/11/2021 (AM) 01/11/2021
Corrections:


Miscellaneous/Other
Outstanding
12/31/2020
Underground residential building

Miscellaneous/Other
Outstanding
12/31/2020
5th floor partial ri

Miscellaneous/Other
Outstanding
12/31/2020
4th floor unit ri

Miscellaneous/Other
Outstanding
12/31/2020
5th, 4th, 3rd floor halls partial ri

Miscellaneous/Other
Outstanding
12/31/2020
3rd floor partial ri

Miscellaneous/Other
Outstanding
12/31/2020
3rd floor west final

Miscellaneous/Other
Outstanding
01/11/2021
2nd floor east partial final

Electrical Rough-in Inspection Partial Pass 1/13/2021 (8:00 - 10:00) 1/13/2021 (AM) 01/13/2021
Corrections:


Miscellaneous/Other
Carried Forward
01/13/2021
2nd floor ri

Electrical Rough-in Inspection Partial Pass 1/27/2021 (8:00 - 10:00) 1/27/2021 (AM) 01/27/2021
Corrections:


Miscellaneous/Other
Outstanding
01/13/2021
2nd floor ri

Miscellaneous/Other
Outstanding
01/27/2021
Service inspection Partial 1st floor ri

Electrical Rough-in Inspection Partial Pass 1/29/2021 (8:00 - 10:00) 1/29/2021 (AM) 01/29/2021
Corrections:


Miscellaneous/Other
Outstanding
01/29/2021
1st floor ri

Electrical Rough-in Inspection Partial Pass 2/5/2021 (8:00 - 10:00) 2/5/2021 (AM) 02/05/2021
Corrections:


Miscellaneous/Other
Comment Only
02/05/2021
Unit ri

Electrical Rough-in Inspection Partial Pass 3/8/2021 (12:30 - 2:30) 3/8/2021 (PM) 03/08/2021
Corrections:


Miscellaneous/Other
Carried Forward
03/08/2021
Service inspection

Electrical Rough-in Inspection Partial Pass 3/12/2021 (10:00 - 12:00) 3/12/2021 (AM) 03/12/2021
Corrections:


Miscellaneous/Other
Carried Forward
03/12/2021
Service inspection

Miscellaneous/Other
Carried Forward
03/12/2021
5th and 4th floor ceiling ri common area’s

Electrical Rough-in Inspection Partial Pass 5/17/2021 (12:30 - 2:30) 5/17/2021 (PM) 05/17/2021
Corrections:


Miscellaneous/Other
Carried Forward
05/17/2021
Service inspection

Miscellaneous/Other
Carried Forward
05/17/2021
5th and 4th floor ceiling ri common area’s

Miscellaneous/Other
Carried Forward
05/17/2021
3rd and 2nd floor hallway ri 1st floor hard lid area

Electrical Final Inspection Partial Pass 5/19/2021 (12:30 - 2:30) 5/19/2021 (PM) 05/19/2021
Corrections:


Miscellaneous/Other
Outstanding
05/19/2021
5th floor final ok

Electrical Final Inspection Partial Pass 5/20/2021 (12:30 - 2:30) 5/20/2021 (PM) 05/20/2021
Corrections:


Miscellaneous/Other
Carried Forward
05/20/2021
4th floor final

Electrical Rough-in Inspection Partial Pass 6/3/2021 (10:00 - 12:00) 6/3/2021 (AM) 06/03/2021
Corrections:


Miscellaneous/Other
Carried Forward
06/03/2021
Service inspection

Miscellaneous/Other
Carried Forward
06/03/2021
5th and 4th floor ceiling ri common area’s

Miscellaneous/Other
Carried Forward
06/03/2021
3rd and 2nd floor hallway ri 1st floor hard lid area

Miscellaneous/Other
Comment Only
06/03/2021
2nd floor entry hard lid ri 1st floor common area’s ceiling ri

Electrical Rough-in Inspection Partial Pass 6/15/2021 (10:00 - 12:00) 6/15/2021 (AM) 06/15/2021
Corrections:


Miscellaneous/Other
Carried Forward
06/15/2021
Service inspection

Miscellaneous/Other
Carried Forward
06/15/2021
5th and 4th floor ceiling ri common area’s

Miscellaneous/Other
Carried Forward
06/15/2021
3rd and 2nd floor hallway ri 1st floor hard lid area

Miscellaneous/Other
Comment Only
06/15/2021
Crossover lights bottom side

Electrical Final Inspection Partial Pass 6/29/2021 (12:30 - 2:30) 6/29/2021 (PM) 06/29/2021
Corrections:


Miscellaneous/Other
Outstanding
05/20/2021
4th floor final

Miscellaneous/Other
Comment Only
06/29/2021
3rd floor final ok

Electrical Final Inspection Partial Pass 6/30/2021 (12:30 - 2:30) 6/30/2021 (PM) 06/30/2021
Corrections:


Miscellaneous/Other
Comment Only
06/30/2021
2nd floor final ok

Electrical Final Inspection Partial Pass 7/1/2021 (12:30 - 2:30) 7/1/2021 (PM) 07/01/2021
Corrections:


Miscellaneous/Other
Comment Only
07/01/2021
1st floor final

Electrical Final Inspection Failed 7/2/2021 (12:30 - 2:30) 7/2/2021 (PM) 07/02/2021
Corrections:


Miscellaneous/Other
Carried Forward
07/02/2021
Inspection cancelled

Electrical Final Inspection Partial Pass 7/7/2021 (10:00 - 12:00) 7/7/2021 (AM) 07/07/2021
Corrections:


Miscellaneous/Other
Outstanding
07/02/2021
Inspection cancelled

Miscellaneous/Other
Comment Only
07/07/2021
Partial final

Electrical Final Inspection Partial Pass 7/8/2021 (8:00 - 10:00) 7/8/2021 (AM) 07/08/2021
Corrections:


Miscellaneous/Other
Comment Only
07/08/2021
Garage partial final ,remove temp power

Electrical Final Inspection Partial Pass 7/9/2021 (8:00 - 10:00) 7/9/2021 (AM) 07/09/2021
Corrections:


Miscellaneous/Other
Comment Only
07/09/2021
Garage partial final

Electrical Final Inspection Partial Pass 7/14/2021 (10:00 - 12:00) 7/14/2021 (AM) 07/14/2021
Corrections:


Miscellaneous/Other
Comment Only
07/14/2021
Partial final

Electrical Final Inspection Partial Pass 7/15/2021 (10:00 - 12:00) 7/15/2021 (AM) 07/15/2021
Electrical Rough-in Inspection Passed 8/13/2021 (12:30 - 2:30) 8/13/2021 (PM) 08/13/2021
Corrections:


Miscellaneous/Other
Outstanding
06/15/2021
Service inspection

Miscellaneous/Other
Outstanding
06/15/2021
5th and 4th floor ceiling ri common area’s

Miscellaneous/Other
Outstanding
06/15/2021
3rd and 2nd floor hallway ri 1st floor hard lid area

Miscellaneous/Other
Comment Only
08/13/2021
Crossover ri

Electrical Final Inspection Passed 9/13/2021 (8:00 - 10:00) 9/13/2021 (AM) 09/13/2021