PREL202000923
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Electrical Rough-in Inspection | Failed | 3/13/2020 (2:30 - 3:30) | 3/13/2020 (PM) | 03/13/2020 |
|
Corrections:
Miscellaneous/Other
Carried Forward
03/13/2020
Treatment rooms require wiring methods per 517
|
||||
| Electrical Rough-in Inspection | Partial Pass | 3/18/2020 (10:00 - 12:00) | 3/18/2020 (AM) | 03/18/2020 |
|
Corrections:
Miscellaneous/Other
Resolved
03/18/2020
Treatment rooms require wiring methods per 517
|
||||
|
Miscellaneous/Other
Comment Only
03/18/2020
Wall RI- ok
|
||||
| Electrical Rough-in Inspection | Passed | 5/19/2020 (10:00 - 12:00) | 5/19/2020 (AM) | 05/19/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/19/2020
Above ceiling- ok
|
||||
|
Miscellaneous/Other
Outstanding
05/19/2020
Need letter for em in procedure rooms. Spoke to contractor.
|
||||
| Electrical Final Inspection | Passed | 6/5/2020 (12:30 - 2:30) | 6/5/2020 (PM) | 06/05/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/05/2020
Final- ok
EM lights installed in procedure rooms.
|
||||